FIRAT ONER, Lead Construction Engineer

FIRAT ONER

Lead Construction Engineer

TANAP

Location
Türkiye
Education
Bachelor's degree, Civil Engineering
Experience
23 years, 6 Months

Share My Profile

Block User


Work Experience

Total years of experience :23 years, 6 Months

Lead Construction Engineer at TANAP
  • Türkiye - Erzurum
  • My current job since March 2016

• Managing the EPCM ( Worley Parson ) project construction teams
• Construction & Commissioning of pipeline including Compressor Station, Metering Station and Block Valve Stations (lot1, spread1: 205km, 56 inch )
• Coordinating and assisting construction team
• Reviewing of principal contractor procedures, documents, specifications
• Monitor and manage all site activities to ensure objectives are accomplished within the prescribed time frame and budget parameters.

Senior Project Engineer at GTL International
  • Iraq - Basra
  • November 2014 to December 2015

Managing the many aspects and various civil design contractors associated with the Greenfield development of a 200kbpd Central Processing Facility (CPF).
Managed Geotechnical consultant during borehole investigations and early civil works cut/fill analysis
Managed Geotechnical consultant during borehole investigations and early civil works cut/fill analysis
Prepared FEED documents
Performing Geo-technical and geo-physical investigation at site
Managed piling, geotechnical subcontractors.
Provided construction support to site team and construction subcontractor during construction, including site visits as required and site based with rotation.

Construction Superintendent at DNO International
  • Iraq
  • September 2013 to November 2014

• Review of CTRs
• Reviewing of design documents and drawings
• Managing the PMC, EPC project construction teams
• Monitoring cost control and schedule
• Review of all contractor method statements and task risk analysis.
• Performing Geo-technical and geo-physical investigation at site
• Reviewing of principal contractor procedures, documents, specifications
• Evaluating the technical bids
• Coordinating and assisting construction team
• Construction of ROWs and access roads; leveling, grading works
• Construction & Commissioning of 42km pipeline (various sizes, 8”, 16” and 36”) on the rocky and mountainous terrain
• Construction of all foundations (equipment’s, tanks, pipe racks, pipe supports, sleepers and buildings)
• Installation of steel structure, equipment’s (including pumps)

Construction Specialist at BP Caspian
  • Azerbaijan
  • June 2012 to September 2013

Reporting to the Line Manager; take responsibility for the coordination of site activities through the construction supervisors; direct responsibility on management of site subcontractors. Ensure the implementation of HSE management system at site with particular reference to their area of operation.

• Monitor and manage all site activities to ensure objectives are accomplished within the prescribed time frame and budget parameters.
• Reviewing of principal contractor procedures, documents, specifications
• Review of all contractor method statements and task risk analysis.
• Coordinating and assisting construction team
• Construction of Pump Station and Block Valve Stations
• Pipeline construction & commissioning, Re-routing works
• Land sliding works, River crossing works and Security fortification works
• Performing Geo-technical and geo-physical investigation at site

Construction Superintendent at Kuwait National Petroleum Company (KNPC)
  • Kuwait
  • January 2011 to May 2012

NEW ACID GAS REMOVAL PLANT in MINA AL-AHMADI REFINARY (406 million USD, Brownfield Project

Civil Superintendent at Maire Tecnimont SpA
  • United Arab Emirates
  • June 2008 to September 2010

Borouge II Project, (Polyolefin Unit, Product Handling & Marine Works

Construction Manager at GAMA INDUSTRY
  • Saudi Arabia - Jeddah
  • August 2006 to May 2008

• 29, 000 m3 concrete ( equipment foundations, buildings, piperack and sleepers, paving, ...)
• 6, 250 ton structural steel
• 6, 100 ton equipment
• 220, 000 WDI piping
Job Description: Reporting to the Project Manager; take responsibility for the coordination of site activities through the Construction Superintendents & Supervisors; direct responsibility on management of site.
I have been worked in that project for Construction Manager with first tier subcontractor. My responsibilities, all the civil, structural, mechanical & piping activities related with EPPE and LLDPE plants. Prepare daily report on-site, analyze work progress. Strong cooperation with Project Management and Client responsible on Engineering Department. Ensure the Implementation of all HSE procedures and standards for the areas or activities.

Civil & Structural Coordinator at GAMA INDUSTRY
  • Saudi Arabia
  • January 2005 to August 2006

• 110, 000 m3 excavation
• 116, 000 m3 concrete
• 156, 000 m2 formworks
• 69, 000 m2 sliding formworks
• 32, 000 tons structural steel, gratings and hand rails manufacturing, painting and erection
• 93, 000 m2 building cladding

Check and control the specific Construction Schedule per discipline if in line with general site planning curves. Manage and control the subcontractor team. Prepare daily report on-site, analyze work progress. Strong cooperation with Project Management and Client responsible on Engineering Dept. Ensure and approve field modification after manufacturing defects detection. Verify and approve field changes during assembly. Prepare ordinary weekly report. Ensure any addition or change to the technical drawings according to Field requirements. Be responsible for reviewing of site technical queries, including field sketches and modifications to any project engineering drawings, as required. Issue any supply non-conformities and follow-up the relevant resolution.

Civil Supervisor at Berri Gas Plan
  • Saudi Arabia - Jubail
  • April 2003 to January 2005

Oversaw daily activities, including formwork, rebar work, concrete placement, and site work, for the construction of a 30 years old Gas Plant. Performed duties of

Construction Site Engineer at ENKA
  • Türkiye
  • July 2000 to March 2003

. Oversaw daily activities, including formwork, rebar work, concrete placement, and site work, for the construction of a 20 hectare compound consisting of cooling towers, water treatment plant and switchyard. Performed duties of Assistant Supervisor for formwork, rebar and concrete placement at site.

Education

Bachelor's degree, Civil Engineering
  • at METU ( Middle East Technical University )
  • June 2000

Qualifications/Certificates

Specialties & Skills

Construction Management
civil engineer
Helical Screw Piles
Oil and Gas
Project Management
BUDGETING
CUSTOMER RELATIONS
ENGINEERING
MICROSOFT POWERPOINT
MICROSOFT WORKS
NATURAL GAS
QUALITY CONTROL
TÉCNICAS DE SUPERVISIÓN
UTILITIES

Languages

English
Expert
Italian
Beginner
Turkish
Native Speaker