TBM Responsible
Salini Impregilo
مجموع سنوات الخبرة :16 years, 0 أشهر
Project Name : Abu Homour Watar Tunnel Project
Description : The Project aimed at Designing and constructing
tunnel by mix shield TBM at AbuHomour for Water
Drainage System.
Responsible For
Planning and Implementing work schedule from initial stage to execution.
Implementing maintenance schedules and carrying out periodic checks to ensure performance of Tunnel Boring Machine (TBM) and maintaining requisite documents for the same.
Provide technical and other support to supervisors and sub-contractors to ensure that safety, time, cost and quality objectives are optimized.
Hand on experience of change cutters in different earth conditions.
Responsible for Assembly and commissioning of TUNNEL BORING MACHINE (TBM).
Responsible for All utilities work and Dewatering system of sites
Project Name : Delhi Metro Rail Project-CC-32
Description :The project aimed at constracting of tunnel by EPB
Mix shield TBM from Palam to Indra Gandhi
International Airport.
Responsible For
Responsible for Assembly and commissioning of TUNNEL BORING MACHINE (TBM).
commissioning and Repairing of Hydraulic Pumps etc.
Monitor usage of spare/wear parts and ensure sufficient stock is kept on site.
Handling maintenance of HYDRAULIC RIG (Boring Machine), Grouting Plant, TFC-280, TATA320 cranes, P&H-440 CRANES etc.
Involving finalization of technical specifications, material & scheduling, progress monitoring, site management & manpower planning, safety, etc.
Project Name : Kolkata Metro Rail Project (UG-2)
Client : Kolkata Metro Rail Corporation Ltd.,
Description : The project aimed at designing and constructing of
tunnel by EPB shield TBM at Subhas Sarovar,
Phoolbagan, Sealdah.
Responsible For
Planning and Implementing work schedule from initial stage to execution.
Implementing maintenance schedules and carrying out periodic checks to ensure performance of Tunnel Boring Machine (TBM) and maintaining requisite documents for the same.
Provide technical and other support to supervisors and sub-contractors to ensure that safety, time, cost and quality
change cutters in different earth conditions.
Responsible for Assembly and commissioning of TUNNEL BORING MACHINE (TBM).
Hand on experience of commissioning and Repairing of Hydraulic Pumps etc.
Monitor usage of spare/wear parts and ensure sufficient stock is kept on site.
Handling maintenance of HYDRAULIC RIG (Boring Machine), Grouting Plant, TFC-280, TATA320 cranes, P&H-440 CRANES etc.
Involving finalization of technical specifications, material & scheduling, progress monitoring, site management & manpower planning, safety, etc.
Project Name : Delhi Metro Rail Project - BC - 24.
Client : Delhi Metro Rail Corporation Ltd., Delhi.
Description : The project aimed at designing and constructing of
tunnel by shield TBM at Khan Market, JLN Stadium
and Jangpura Stations, Udyog Bhawan, Lajpat Nagar,
etc