QA / QC Supervisor Mechanical at China Railway Construction Corporation CRCC
  • Saudi Arabia - Dammam
  • My current job since January 2020

Plan, develop, and monitor the Quality Control Section activities including providing technical support and advise on QA/QC and best practices on Industry matters associated with design and inspection of new Construction to support the department and the division in ensuring safe and reliable operations.
Leading Failure investigations, root cause analysis and technical recommendations to department manager to improve integrity and reliability of Construction works at all stages.
Develop and review of Quality procedures required for improvements inspection and methods for reducing down time.
Plan, direct, supervise, review effective implementation of the QA/QC System in Company's Construction works which are designed to improve Health, Safety & Environment, Operability, process efficiency and production increase in accordance with the latest international and company standards & codes of practice.
Ensure that company QA/QC requirements are fulfilled and demonstrated during the entire Construction works and regular routine activities.
Ensure Quality Control during Planning and Implementing, Turnaround execution through all stages from Concept Design/Engineering, Production of Tender for Construction, and Procurement of services/materials till commissioning.
Assist the Manager Planning, Scheduling and Turnaround in developing scope of work for Third Party Inspection Contractual Agreement and monitor the effectiveness of Contractors’ performance.
Identify and recommend action plans in solving operation and process problems to resolve and prevent quality issues.
Review, verify and endorse company Turnaround Project Quality Plan and QA procedures and standardize required Inspection & Test Plan (ITP) /QA/QC Inspection checklist for improving QA/QC System.
Review and endorse submission of the Contractors and sub-contractor’s Project Quality Program and verify its implementation in relation to their supplied products and services. Submit recommendations on supplier’s performance and capabilities with regard to QA/QC.
Carryout Quality Audits and Site/Shop surveys of Manufacturers, Contractors/Consultants and Suppliers as required.
Monitor and verify all non-conformities raised and assist Management Team in taking effective corrective actions for their closure.
Ensure that all inspection requirements have been fulfilled satisfactorily according to final approved drawings/documents and supplier quality plan.
Manage and supervise all TPI, Contractors QA/ QC Engineers and QC inspectors during Construction works of all stages.
Safeguard own Health and Safety, as well as that of the fellow employees, by paying attention to safe work practices, maintaining a safe work environment and complying with applicable HSE requirements.
Take action to INTERVENE and STOP any un-safe activity or non-compliance with HSE requirements, if witnessed, and report the incident - regardless of your position or that of the transgressor.

Sr Mechanical Inspector / Engineer at Turner Saudi Arabia AYJAL housing (South Dhahran home ownership
  • Saudi Arabia - Dhahran Al Janoub
  • October 2017 to November 2019

Providing day-to-day direction for inspection of new facilities in line with engineering & Saudi Aramco standards
Conducting inspection of:
Installation & inspection of Pressure vessels, Heat exchangers, Skids, Pumps, Colum’s and Drums.
Joints preparation by verifying the joint dimension, fit-up, weld joint cleanliness, quality of individual process, placement and sequence of individual weld passes, interpass cleaning (there is no bimetallic contamination), interpass temperature and time intervals in weld cycle.
Welding electrodes baking and issuance/return record.
Pipe spool internal cleaning (air blowing) prior installation
Pipe laying inspection at pipe rack and sleeper way
Drafting inspection reports, pre and post testing and inspection (T&I) reports, worksheets and non-compliance reports and follow-up, Analyze and closing worksheets and non-compliance reports.
Preparation of (LBE) log book entries of finding during surveillance on-site inspection.
Inspect each job site for unsafe conditions that could cause injury, death or financial loss to the company or property.
Valve installation
Witnessed field valve testing (body test, seat test and back seat test)
Witnessed correct type and size of Gasket installation for intended for services.
Bolt torqueing and bolt tensioning activities
Reviewing documents of:
Receiving material as per applicable material specification and international code and standard.
Receiving Welding consumables as per ASME sec II C.
Review of WPS and PQR prior to submit for client’s approval.
Undertaking:
Pretest punch list as per approved isometric drawing and P&ID
Hydro testing and pneumatic testing
Preparing final punch list in line with reference approved latest revised isometric drawing and P&ID drawings
Developing punch list items during line checking as per project specifications & standards
Analyzing piping test packages prior to pneumatic / hydro testing
Assisting sub-contractor QC Inspector in inspections and review of piping & closing of NCR
Generating inspection reports, worksheets, non-compliance reports, log book entries and onsite inspection findings
Managing:
Installation & inspection of lift station for oily water, sanitary water and storm water sewer systems
Calibration of equipment based on the method of statement & vendor's recommendation
Creating punch list through MCC walkthrough for plumbing, fire-fighting equipment and components installation
Implementing project, coordinating CP installation & commissioning activities for CDS / CHCD systems
Upgrading existing CP system and performing:
Interference test with foreign pipelines at crossing locations
Inspection (RFI) as per the latest approved (ITP)
Bolt tightening activities to produce necessary documentation
Inspection for shaft Alignment (1st, 2nd and Hot Alignment) with minimum allowable Tolerance
Inspection of platforms, handrails, ladders, overhead traveling crane as per approved drawing and standards
Heading pre-commissioning activities of rotating equipment, procedures reviews for water flushing, chemical cleaning, de-greasing, air blowing, oil flushing, motor solo run, mechanical run and operational tests
Dealing with technical bids evaluation, detail and field engineering / modifications / response to site technical queries, review of data sheets, IOMs, Fat reports, GAD / cross sectional drawings, P&IDs, analysis data, modification schemes & mechanical seals
Supervising installation & commissioning of:
Reverse osmosis plant (SO SAFE, AQUA FINA)
Electric water heater made by super Asia,
Multi stage booster pumps for raw water and drinking water system
Caterpillar gas engine, heavy duty niigata furnace / diesel oil engine, gas turbine (turbo mach) including waste heat recovery boiler, boiler feed pumps and inline gear pump

QA at Saudi Aramco Oil and Gas Company Bureau Veritas Saudi Arabia Eastern Region
  • Saudi Arabia - Jubail
  • September 2011 to February 2017

Duties & Responsibilities:
Responsibilities will include but not be limited to the following:
 Responsible for the thorough and accurate calculation of pressure testing of various type of piping material used in UG and AG metallic an nonmetallic used in industry.
 Coordinating execution, hydro testing with planning and QA/QC activities. Monitoring hydro test package preparation.

 Responsible for reinstatement of hydro tested piping and monitoring, coordinating and follow up the site and sign off the packages to hand over to the pre-commissioning team for target setting, progress and task analysis of test packages to make ready for testing.

 To achieve the target, coordinate test packages flow by monitoring and coordinate the verification and transmittals of test packages to respective departments such as Engineering, QA/QC, and Construction for punch attending, to release the package for line testing.
 Responsible for overseeing test booth operation including extensive training of employees in proper equipment inspection, maintenance, record of test and hydro testing procedure per company policy.

 Performs leads or otherwise participates in the coordination of Construction work for onshore projects done by contractors to ensure conformance to the company’s specifications and standards.
 Ensures implementation of the company project procedures for the safe and efficient execution of construction projects.
 Coordinates with contractors’ onsite the recording, tracking of hydro testing.
 Evaluates and develops solutions to problems on site, which arise in the execution of projects.
 Maintains an established inspection strategy and plan
 Manages site supervisors and verifies that all punch YES items Closed prior to execution of hydro testing

Engineer at Izhar construction Pvt. Ltd
  • Pakistan - Lahore
  • November 2009 to August 2011

Duties & Responsibilities:
Responsibilities will include but not be limited to the following:
 Achieved project deadline by managing/scheduling/leading contractors with a flexible staff of 25 construction and plant personnel, working extended hours for months, fast-tracking project.
 Led request for quotations and Construction Contractor selection and management including routine site supervision ensuring quality of work and specifications compliance as well as OSHA safety guidelines.
 Wrote operational procedures for new system to incorporate in daily plant operations and improve efficiency.
 Prepared commissioning and start-up, including training, and maintenance.
 Scheduled meetings with local, county, state and federal officials and the general public to address any concerns about on-going or future projects.
 Issued project related correspondence to internal and external clients.
 Attended and facilitated Preconstruction Conferences, Utility Coordination Meetings, and weekly meetings to discuss progress or concerns on projects.
 Made decisions on and processed change orders for alterations or for additional work on projects.
 Planned logistical movement of equipment and materials.
 Correspondence with the project owner and engineer through Change Orders, RFIs, and Submittals
 Completed and disbursed RFIs to subcontractors and addressed any questions or concerns
 Strengthened skills in contract negotiation and gained a competent understanding of Inspected and verified blueprints for the 2 high-profile projects and addressed corrections as needed
 Facilitated subcontracts for multiple company projects and completed submittal forms to address product needs
 Assisted site managers with on-site visits and meetings with sub-contractors
 Completed and disbursed RFIs to subcontractors and addressed any questions or concerns
 Strengthened skills in contract negotiation and gained a competent understanding of project oversight
 Created a schedule for the construction levels of manpower, materials, and equipment, including work with suppliers, subcontractors, while also conducting and supervising work inspections.
 Attended technical and progress meetings with architects and consultants; managed submittal, RFIs, and NCRs.

Plumbing Supervisor at Eden Housing Pvt. Ltd. Lahore Pakistan Eden Lane Villas, & White House (Mahal) HVAC &
  • Pakistan - Lahore
  • May 2006 to August 2008
Supervisor Plumbing at Eden Developer’s Pvt Ltd
  • Pakistan - Lahore
  • March 2002 to January 2006
Plumbing Supervisor at S.M Mehboob and Company Akbar & Associate MacDonald, Restaurant, & Lums University
  • Pakistan - Lahore
  • September 2000 to February 2002

• Field supervisory mechanical engineering position in building construction management. Application of mechanical engineering expertise on mechanical systems - specifically; underground piping combined Fire and portable water supply System, Storm water System, Heating Ventilation and Cooling (HVAC), plumbing and fire protection systems as well as Building Automation and Temperature Control Systems (BAS). Supervision of building; mechanical installations, testing and commissioning of HVAC, plumbing, Utility tanks and Pumping stations equipment with Construction drawings, One-lines, Shop drawings, Material submittals, and appropriate mechanical codes and requirements (IMC, AWWA, ASTM, IPC, IBC, ASHRAE and NFPA, SMACNA and other related building codes and standards)
• Responsible for monitoring and inspection of on-site mechanical installation and testing work activities. Provides technical guidance to contractors to ensure that the permanent works are constructed in accordance with applicable codes, standards, and approved drawings and specifications.

Supervisor at Eden Developer’s Pvt Ltd Eden Developer’s Pvt Ltd Eden Heigh
  • Pakistan - Lahore
  • September 1999 to August 2000

• Field supervisory mechanical engineering position in building construction management. Application of mechanical engineering expertise on mechanical systems - specifically; underground piping combined Fire and portable water supply System, Storm water System, Heating Ventilation and Cooling (HVAC), plumbing and fire protection systems as well as Building Automation and Temperature Control Systems (BAS). Supervision of building; mechanical installations, testing and commissioning of HVAC, plumbing, Utility tanks and Pumping stations equipment with Construction drawings, One-lines, Shop drawings, Material submittals, and appropriate mechanical codes and requirements (IMC, AWWA, ASTM, IPC, IBC, ASHRAE and NFPA, SMACNA and other related building codes and standards)
• Responsible for monitoring and inspection of on-site mechanical installation and testing work activities. Provides technical guidance to contractors to ensure that the permanent works are constructed in accordance with applicable codes, standards, and approved drawings and specifications.

Mechanical Technician at Sitara Group of Industries (Sitara Energy Pvt Ltd)
  • Pakistan - Faisalabad
  • July 1997 to February 1999

• Execution, commissioning and inspection of Lift station/Pump station for Fire water, hydro carbon, Oily water, sanitary water and Storm water sewer systems and irrigation. Assures installation of various type of Mechanical equipment’s, HVAC equipment’s and Plumbing fixtures.
• Execution, Installation and commissioning of Reverse osmosis plant, swimming pool caterpillar gas engine, heavy duty Niigata furnace / diesel oil engine, Gas turbine (Turbo Mach) including with waste heat recovery boiler, feed pumps and protection devices etc.

Plumbing Supervisor at Pakistan Services Ltd (PSL) Pakistan Services Ltd (PSL) Pearl Continental Hotel
  • Pakistan - Lahore
  • July 1996 to May 1997

Execution, commissioning and inspection of Lift station/Pump station for Fire water, hydro carbon, Oily water, sanitary water and Storm water sewer systems and irrigation. Assures installation of various type of Mechanical equipment’s, HVAC equipment’s and Plumbing fixtures.

Field QA Engineer/Inspector Mechanical
  • to

Capability to handle material inspection, material demands, drawing issues, progress and quality of work, execution and commissioning according to applicable code and standards.
•Knowledge of wells, video logging for water wells, casing repairs, submersible turbines, submersible pumps, repair of faulty casings etc.
•Knowledge of Wet and Dry fire Protection piping, fuel piping, chill water and hot water piping, Package Unit, AHU, FCU, Ducting etc.
•Review the Drawings, procedures and method of statement which are to be use have been approved before starting the job.
•Conduct joint site inspection together with subcontractor’s QC inspector and owner’s representative prior for to close out NCR's.
•Writes inspection reports, worksheets, and non-compliance reports and makes log book entries onsite inspection findings and maintain inspection records.
•Ability to perform deliverables and documentation such as calculations, drawings and specifications related to plumbing and piping systems.
•Ability Perform review on design functions including equipment selection, system sizing, fixture calculations, product specifications and design layouts for domestic plumbing systems, industrial plumbing systems and medical gas.
•Research and provide advice on new and innovative products and technologies.
•Attend and participate in industry related conferences and seminars.
•Ability to direct and lead a group of junior plumbing design engineers.
•Assures for proper handling and calibration procedure of various type of Equipment based on the method of statement & vendor's recommendation.
•Generate punch listing through MCC walkthrough for Plumbing and Fire Fighting equipment and components installation.
•Participate in Design Review and value engineering with respect to save cost of project and reliability of Systems and equipment’s.
•Execution, commissioning and inspection of Lift station/Pump station for Fire water, hydro carbon, Oily water, sanitary water and Storm water sewer systems and irrigation. Assures installation of various type of Mechanical equipment’s, HVAC equipment’s and Plumbing fixtures.
•Execution, Installation and commissioning of Reverse osmosis plant, swimming pool caterpillar gas engine, heavy duty Niigata furnace / diesel oil engine, Gas turbine (Turbo Mach) including with waste heat recovery boiler, feed pumps and protection devices etc.
•Field supervisory mechanical engineering position in building construction management. Application of mechanical engineering expertise on mechanical systems - specifically; underground piping combined Fire and portable water supply System, Storm water System, Heating Ventilation and Cooling (HVAC), plumbing and fire protection systems as well as Building Automation and Temperature Control Systems (BAS). Supervision of building; mechanical installations, testing and commissioning of HVAC, plumbing, Utility tanks and Pumping stations equipment with Construction drawings, One-lines, Shop drawings, Material submittals, and appropriate mechanical codes and requirements (IMC, AWWA, ASTM, IPC, IBC, ASHRAE and NFPA, SMACNA and other related building codes and standards)
•Responsible for monitoring and inspection of on-site mechanical installation and testing work activities. Provides technical guidance to contractors to ensure that the permanent works are constructed in accordance with applicable codes, standards, and approved drawings and specifications.

Education

Bachelor's degree, Mechanical Engineering
  • at Preston Institute of Management Sciences and Technology
  • June 2006

ISO 9001:2015 Quality Management System API-570 (Process Piping Inspector) Dammam, KSA, valid up to 2021 API-510 (Pressure Vessel Inspector) Dammam, KSA, valid up to 2021 API-577 (Welding and Metallurgy) Dammam, KSA, valid up to 2021 Certified ASNT Level II as per SNT-TC-1A UT, PT, MT, RT valid up to 2021 (LEED Green Building) Certified Leadership in Energy and Environment Design GBCI, Dammam, KSA, valid up to 2021

Specialties & Skills

Oilfield Services
Mechanical Design
Plumbing Design
HVAC Design
Quality Inspection
DOCUMENTATION

Languages

English
Expert

Training and Certifications

Pressure Vessel inspector (API-510) (Certificate)
Date Attended:
September 2015
Valid Until:
September 2018
Process piping Inspector (API-570) (Certificate)
Date Attended:
November 2018
Valid Until:
November 2020
ASNT LEVEL-II (SNT-TC-1A UT, PT, MT, RT ) (Certificate)
Date Attended:
September 2016
Valid Until:
September 2021
Welding (API-577) (Certificate)
Date Attended:
April 2015
Valid Until:
April 2021
LEED GA (Certificate)
Date Attended:
January 2015
Valid Until:
March 2019

Hobbies

  • Reading Technical Books, Bedminton ,Cricket