SR.PROCUREMENT ENGINEER
SABIC
Total years of experience :36 years, 8 Months
Jan 2007 - To Date Sr. Procurement Engineer
SABIC - (Saudi Basic Industries Corporation)Engineering & Project Management, Jubail, Saudi Arabia
Nov 2010- To date
SABIC Petrokemya CBR Project & Millisecond Furnace Project
Managing & Monitoring the progress of EPC Contractor’s Procurement related work such as review of Procedures, Purchase orders, Terms & Conditions, Progress reports, review & approval of additional vendors.
Participated in screening of prospective EPC contractor's capabilities to execute the project effectively:
Assisted in screening of EPC Contractor by evaluating their bids/tenders about their Procurement execution capabilities.
Maintain SABIC E&PM vendor approval list and approval of Engineering Contractor vendor list
Carried out Procurement activities for the Long Lead items such as issuing Quotation requests, receiving & handling of sealed bids, Commercial evaluation of quotation, lead commercial clarification meeting to negotiate & finalize commercial terms & conditions with suppliers, prepare Quotation summary and give recommendation for award of orders.
Jan 2008- Oct 2010 SABIC Petrokemya Utility Improvement Project
Responsible for entire Procurement cycle on a cradle to grave basis.
Lead Procurement team members, guide and resolve all day to day related issues. As Lead Buyer, lead the team and placed order for equipments/ materials & Services of worth > USD 125 million .Packages include Boiler, Demin& MBP Skid, Air Compressor, BFW & D/L pump, Water Tanks etc.Electrical &Instrumentation and Piping bulk materials.
Jan 2008 to Dec 2009 SABIC IBN-ZAHR Projects
Jan 2007 to Dec 2008SABIC Petrokemya PVC, VCM and U&O Projects
Managing & Monitoring the progress of EPC Contractor’s Procurement related work such as review of Procedures, Purchase orders, Terms & Conditions, Progress reports, review & approval of additional vendors
FAFCO had positioned itself as one of the leading construction companies in the Eastern Province o Saudi Arabia. FAFCO is involved in the General
Construction Projects providing services on EPC to mainly Saudi ARAMCO.
Project: Waste Water Treatment Plant
India
Dec 1992 to 2003
Air Compressor Manufacturing & Automotive Equipments
May 1985 to November 1992
Heavy metal, Structural and Piping Fabrication Personal Details
Date of Birth : 10.03.1966
Marital status : Married
Nationality : INDIAN
Passport No : F7400686
Hobbies : Hearing music and reading books
Reference
Mr. Luai Al-Tayeb,
Projects GM, SABIC E&PM,
Saudi Arabia
Mr. Abdullah Al-Shahrani,
Project Manager, SABIC E&PM Saudi Arabia
Preparation of Project Specific Vendor /Contractor list for the approval of the client.
Solicit quotations from approved bidders in accordance with approved procedures and schedules and coordinate bidder's questions and timely responses. Ensure bids are received, opened, recorded and distributed in accordance with the project procedures.
Prepare/Complete Commercial Bid Analysis and makes recommendation for award of orders.
Issuing purchasing order and revisions (change orders) as required.
Monitoring the progress of order of equipments purchase orders from order placement to delivery.
Expedite vendor document/drawing submittals in order to support engineering / construction schedules.
Liaise with Shipping Group and provide all necessary information required for arranging and shipping of equipments
Spare parts co-ordination and issue of PO for 2 year Operation Spares
Preparation of Purchase Order Close out reports and Performance Appraisal/Evaluation report of the Suppliers.
ElGI was established in 1960 and now produces Air compressors and automotive equipments.
Responsible to identify forecasted material for a given series of products requirements from BaaN ERP system and achieve procurement targets on weekly basis.
Reviewing technical, commercial terms, lead-time of parts, and approval of relevant authorities, issues PO’s to the approved vendors.
Responsible to follow up the vendors for delivery of the components based on tracking record.
Responsible to implement new manufacturing means at vendor to improve supply and quality.
Responsible to develop new vendors based on their arrangements like technical, financial, on time delivery, plant and stock facilities and QMS
Responsible to improve on-time delivery, cost reduction and supplier reduction.
Responsible to take CA and PA for repeated rejection
It is a Heavy metal, Structural and Piping Fabrication Company, operates as a main subcontractor of ELGI& ISRO
Responsible to ensure that all assigned fabrication job are carried out in accordance with specifications and schedule and operate shifts.
Responsible to utilize the resources are effect a safe efficient, profitable execution of all assigned tasks.
Responsible to study fabrication drawings, BOM and schedules check and explain to the fabricator.
Responsible to arrange for stages and final inspection of fabricated items as required.
Responsible to ensure self qualify the products from production center.
Responsible to provide maintenance work (preventive & periodic) for key machines