Assistant Resident Engineer
National Development Consultants (NDC).
Total years of experience :19 years, 2 Months
Key Project to Credit:
Rehabilitation & Modernization of Islam Barrage Key Responsibilities as Assistant Resident Engineer:
Responsible for construction supervision of Barrage Works.
Construction Supervision of Main Weir, Sub Weir, Divide Wall, Flank Wall, and Fish Ladder.
Construction Supervision of Concrete, Rawal Bolts, Grouting, Surface Patching, Stone Apron, Friction Blocks & PCC Blocks.
Construction Supervision of Irrigation Colony & Road Works.
Construction Supervision of Rest House, Xen Residence, SDO Residence, Employer Office Complex, Senior Quarters, Junior Quarters, Colony Masjid.
Inspection and checking for all quality-related procedures in the site and ensuring activity at the site is as per the approved method statement and inspection test plan.
Checking of IPC and preparing monthly Progress Reports.
Coordinate with Client & Contractor Staff regarding site issues and timely resolve the issues.
Key Project to Credit:
Kachhi Canal Project Phase 6 (4R)
Key Responsibilities as Assistant Resident Engineer:
Responsible for construction supervision of canal-lining and hydraulic structures such as super passage, canal syphon, cross regulator, tail structure, VRB & watercourse crossings, ensuring flawless execution of the project on time and within budget, aligned with project requirements.
Effectively supervised and managed all site activities to meet goals as defined, provided value-engineering recommendations to maintain desired quality standards through project compliance of piling work/transition wall and checking bar bending schedule.
Coordinate with the contractor’s representative for inspection and meeting about quality problems including the closure of the Non- Conformance Report.
Responsible for inspection and checking for all quality-related procedures in the site and ensuring activity at the site is as per the approved method statement and inspection test plan.
Key Project
Construction of Remaining Sewerage System in the North-West Industrial Zone and south-west-West Industrial Zone at Port Qasim, Karachi.
Key Responsibilities as Assistant Project Manager:
Responsible for overall administration, management, implementation, monitoring and reporting of the project.
Initiate and execute activities of the construction team ensuring adherence to the project & work plans.
Supervise & lead the teams regarding their duties at an optimum level ensuring resources are utilized efficiently.
Identify and resolve alignment, plan & profile or other site issues with the consultants.
Identify and manage project dependencies and critical paths.
Plan & schedule project timelines and milestones using Primavera.
Track project milestones and deliverables on scheduled time.
Coordinate with Consultants and client regarding site issues & timely resolve the issues.
Key Project to Credit:
Nai Gaj Dam, Dadu, Sindh
Key Responsibilities as Assistant Resident Engineer:
Construction Supervision of the Main Dam, Spillway, Intake Structure & Dykes.
Construction supervision of embankment fills, comprising of different materials like Sandy gravel, Random fill, Clay core, Fine filter
Carry out inspection and checking for all quality-related procedures in the site and ensure activity at the site is as per the approved method statement & inspection Test plan.
Managing Site Engineers and inspectors on a daily basis to ensure quality control and a proper reporting system.
Coordinate with the contractor’s representative and Site in charge for inspection and meeting about quality problems Including the closure of Non- Conformance reports.
Checking & verifying method statement & bar bending schedule of Intake Structure.
Key Project
Flood Emergency Reconstruction & Resilience Project, Lahore, Pakistan
Perform all daily inspections and test scope and character necessary to achieve the quality of construction required in the drawings and specifications for all works under the contract.
Carry out inspection and checking for all quality-related procedures in the site and ensure activity at the site is as per the approved method statement and inspection test plan.
Coordinate with the contractor’s representative and Site in charge for inspection and meeting about quality problems including the closure of Non- Conformance Reports.
Taking care of QA/QC documents of the entire project including certificates, calibration, test results, inspection requests, non-conformance reports and site instruction/observations, permanent materials delivered and other QA/QC documents.
Responsible for the closure of the Non-conformance Report (NCR) and Site Instruction (SI).
Responsible for the quality and workmanship of every activity, thorough knowledge of all phases of engineering construction relating to Civil, Irrigation and Structural discipline interfacing the multidisciplinary operations.
Approve the method statement for the activities and checklist based on the specifications of the project.
Key Project to Credit: Development of Al Raqi Exit Border Project (Administration & Residential Colony Buildings) Ministry of Finance, Riyadh, Saudi Arabia Key Responsibilities as Assistant Resident Engineer: Ofering technical advice and construction leadership on projects during the planning and design phases as well as handling design, direction, supervision, coordination and control of the work during the construction phase. Leading a multidisciplinary team of engineers and inspectors in diverse areas encompassing construction, operations, and maintenance activities at the project site. Establishing an efective project quality control procedure and ensuring that they are in accordance with the design specifications, safety standards, and industry best practices. Reviewing construction plans, specifications, and schedules; monitoring the quality of material, ensuring that inspection and method statements are performed, witnessed, and documented for technical accuracy. Accepting ownership for accomplishing projects; analyzing engineering designs and shop drawings; ensuring work project milestones within the planned budget, time, and quality. Liaising with site engineers & QA/QC Engineers and witnessing the field density test, Concrete slump test, Gradation of aggregates, moisture contents of aggregates, concrete compression test, etc. Inspection of material and activities at all stages of project execution Review of design drawings according to client specifications and applicable code/ standard. Providing field engineering support as required to resolve technical and construction problems in design and quality. Javed Ahmed +92 3334707473 javedal2022@gmail.c om
Planned, directed and coordinated activities of construction project consisting of the permanent residential colony (113 houses, dispensary, Masjid, primary school, and market) and supervision of retaining wall (switchyard, earthwork of switchyard), road works, tunnel works and & breast walls.
Drove project excellence by providing project strategy recommendations to enhance project value, ensuring efficient use of project resources, adherence to agreed timelines, and the provision of high quality, reliable and responsive services in line with customer needs and set objectives/goals.
Managed the daily activities of construction projects and ensured successful completion of the project, analyzed project needs, conformed to IPC, bar bending schedule, the proposal submitted by Contractor, and recommended the appropriate level of planning, scheduling, and control of labourers & equipment.
Attended technical meetings and mediated with resident engineers & client regarding site issues engaged in project work, while aiming at satisfying the highest common interest.
Maintained a relentless focus on meeting and exceeding customer needs and expectations. Executed work as per the drawings and ascertained tools and techniques of testing & surveying, and Civil QA/QC tests are properly followed during construction
Kachhi Canal Project Phase 4
Effectively supervised and managed all site resources to meet development goals as outlined, provided value-engineering recommendations to maintain desired quality standards through project compliance of piling work/transition wall and checking bar bending schedule.
Outlined project objectives/ plans and developed plans to execute canal-lining supervision of hydraulic structures such as super passage VRB/DRBs & watercourse crossings, while ensuring flawless execution of the project on time and within budget, aligned with project requirements.
Generated an array of technical reports and highlighted potential deviations/issues with requisite solutions after assessing them for technical feasibility.
Projects
Right Bank Outfall Drain I, Sukkur Barrage Rehabilitation, National Drainage Program, Baluchistan
Key Responsibilities
Delivered solutions leveraging technical competency and industry knowledge for the Hydraulic design of canals & structures.
Demonstrated knowledge of preparing drawings on AutoCAD 2006; developing X sections and calculating the quantities.
Produced design calculations and location maps using AutoCAD 2006 and performed site visits for the collection and supervision of survey/data.
Led the full design and coordination process to ascertain accurate engineering deliverables
Projects
National Bank Sports Complex, Karachi, PC Hotel Gwadar, Pakistan
Key Responsibilities
Responsible for managing project activities, conformance to technical specifications, inspecting steel reinforcement, masonry work & all Structure works as per construction drawings, scheduling, basic and detail engineering.
Prepared bar-bending schedules of structural elements and inspection of formwork and layouts prior to concrete pouring activity.
Provided engineering input for analyzing field density tests, slump tests & compression tests for concrete.
Prepared all associated calculations, reports of manpower, and work progress, ensured the project ran to time/budget, and negotiated with the Consultant for resolving site issues.
Project
Construction of Road from Larkana to Ratodero, Sindh, Pakistan.
Key Responsibilities
Produced as-built drawings & records for every element of the works involved as well as measured actual materials used and reconciled with material ordered; reported and investigated reasons for differences.
Generated an accurate daily diary of resources, including labour, plant, materials, subcontractors, and outputs in liaison with Clients and consultants and the team on-site.
Ensured all quality control procedures were adhered to and works were carried out as per construction drawings & technical specifications.