Sr. Quantity Surveyor
ABV Rock Group
Total years of experience :18 years, 10 Months
Project Detail:
The Security Forces Medical Center, Riyadh (2015 - 2017) 3.3 Billion USD
The Security Forces Medical Center, Jeddah (2017 - Present) 3.3 Billion USD
SFMC Jeddah medical city cover a total Land area of 3.78 Million Sq.km, as well 2 Million Sq.m Built-up area. A Lump Sum type contract following CSI’s Master format of 16 divisions, consisting of Medical Building, Residential Buildings 290 Villas, 10 Single Apartment & 25 Family Apartment, Mosques, Car Parks, Tunnel, Utility Buildings, Non-Medical Facilities & Infrastructure.
Department: Project Control
Reporting: Project Control Manager
Duties Performing:
Preparing and submitting monthly valuations, Coordination, joint verification and finalizing with consultant.
Measure Quantities by analyzing phase & IFC drawings, compare with Tender BOQs/Drawings, and determine variation items and the impact of variations on Budget.
Check and verify Material Purchase Request (MPR) and compare with BOQ Quantities.
Prepare Actual and forecast progress report to monitor construction actives on monthly basis and to compare with planned progress.
Check and Verify sub-contractor and Supplier Invoices ensure quantities & specs are in line with project specs.
Review Log, extract site daily activities, and evaluate executed work to prepare interim payments.
Co-ordination meeting with Consultant follow up to get approval
Co-ordination with construction Team to compare actual progress with Work Inspection Reports.
Project Detail:
King Faisal Specialist Hospital & Research Center Expansion Projects Al Riyadh, Saudi Arabia
• King Abdullah Center for Cancer & Liver Diseases (KACC Building) - 21 Story multi Hospital Building
• Central Plant Building - Centralized Electrical Substation, Boiler and Chiller Plant
• Single Female Housing Complex-H - 11 Story Residential Building for Hospital Staff
• Royal Wing & EMS Building - Hospital Building for Royal Families
• Service Tunnel & Site Developments-Tunnel for underground access interconnecting buildings and for Electrical & Mechanical Transmission & Distribution System
Reporting: Project Control Manager
Duties Performed:
• Prepare Take off (QMS) from IFC Drawings for monthly Payments & Certification from consultant
• Coordination with consultant team for joint verification of monthly valuations.
• Comparison of Design & Tender drawings, identifying variation items, if any
• Co-ordination with Variation department to facilitate timely notice of variation items to client
• Prepare the monthly Interim Payment Application to the sub-contractors.
• Monitor WIR, TER & PIR Log and evaluate executed work to prepare interim payments
• Involved in tendering works for new projects
Project Detail:
Rebuilding Sustainable Communities School Reconstruction in Pakistan
12 primary school and 2 high schools building
Client: CDM Smith
Consultant: CDM Smith
Responsibilities
Preparing monthly Invoices and update final quantity estimates based upon actual progress of work.
Preparation of Bar Bending Schedule as per Drawing.
Check and verify the invoices of subcontractor.
Responsibilities
1- Quantity Take Off
2- Prepare bar Bending Schedule.
3- Prepare monthly payment certificate.
4- Joint Inspection and recommendation of monthly payment certificate with consultant.
5- Verification and checking Contractor and Sub Contractor Payment application.
Project Detail:
Saudi Fund for development project, Reconstruction of University of Azad Jammu & Kashmir, chattar kalaas campus, Muzaffarabad, Azad Jammu & Kashmir.
Responsibilities
Responsibilities
1- Quantity Take Off from approved shop drawings.
2- Prepare bar Bending Schedule.
3- Prepare monthly payment certificate.
4- Joint Inspection and recommendation of monthly payment certificate with consultant.
Project Detail:
Earthquake Additional Financing Project (Part-Z) - IDA Credit 3689-1/Pak (Over 450 buildings in PC-1 including Primary schools, Middle schools, Local Government Offices Agriculture department Planning & Development Department).
Consultant: Engineering and Management Survives (EMS)
Donor: World Bank IDA Credit 3689-1/Pak
Responsibilities
Measure quantities by analyzing design drawings
Prepare BOQ using schedule of rate (CSR) and cross check with Engineer (EMS) BOQ.
Bid Evaluation: Check formulas, Rates, Amount, Hard & Soft Copies for all the bidders, prepare comparative statement In order to determine the lowest evaluated bidder.
Proof Check the quantities in the measurement books (MB) to ensure that work executed with technical drawings and specification.
Check and verify monthly Payment certificates of Contractors submitted through consultant.
Compilation of contractor’s payment on a standard and prescribed form.
Prepare deviation statement (variation and digression) and completion certificate.
Responsibilities
Building Layout as per Drawing.
Site Supervision.
Preparation of Monthly Invoices as per work done.
Cost Estimation.
Check and Verify Sub Contractor Invoices.
Preparation of estimate for purchasing martial like cement, sand, Aggregate, Steel, Form work, Scaffolding etc
Continued
Bctchlor in engineering
Diploma of Associate Engineer (D.A.E) is a post secondary program of instructions in Applied Technologies. It includes regular studies having classroom lectures, workshop assignments, labs experiments, industrial projects and industrial tours. D.A.E program duration is three years.
URL removed due to policy violation. Please contact support for further information.