Assistant Manager Electrical
China Huaneng Group
Total years of experience :8 years, 11 Months
• Developed a technically strong maintenance team by providing regular guidance and training to junior employees.
• Assisted the Manager in compilation and modification of annual, quarterly and monthly work plan, and organized the equipment management under the jurisdiction of work group.
• Scheduled 500kV transmission line shut down with NTDC Grid and carried out in house substation maintenance in an effective manner.
• Tested 22kV NARI generator and transformer protections and supervised 10kV WISCOM transformer and motor protections testing during annual maintenance procedure.
• Assessed 500kV switchgear, 22kV generator, and 10kV feeder through high voltage acceptance testing, aligning with GB standards, and safeguarding optimal performance and reliability.
• Achieved uninterrupted power generation for last 8 years by troubleshooting and rectifying faults on electrical equipment.
• Achieved multiple accident free years by strictly following proper safety protocols and conducting regular in-house safety trainings.
• Contributed to the installation of the GT Unit as well as switchyard electrical equipment during the time of commissioning. Played a key role in conducting Site Acceptance Tests (SAT) collaboratively with the maintenance team.
• Diagnosed and analyzed complex circuitry faults for effective and timely solution by managing a risk free working environment.
• Supervised manufacturing and installation of 11kV induction furnace control cabinets.
• Carried out control circuit modification and conducted fault analysis and rectification in a timely manner to facilitate the clients.
● Prepared feasible reports in accordance with IEC 61987 standard and sensor specifications.
● Deployed my technical knowledge in a 2 month training program and studied industry appliances, Single Line Diagram, instruments type and use according to requirement.
• Acquired hand on experience of NIGATA 16V32CLX diesel engine and JENBACHER JGS620 gas engine and administered its maintenance with the team efort.
• Implemented protection; control circuit design and modification to ensure safe operation.
• Consolidated maintenance work by actively participating in routine inspection; evaluating hidden dangers and rectifying the problems in time.
INTERNSHIPS
● Surveyed and analyzed the appliances department and learned about appliances process loop and Single Line Diagrams.
● Studied working principle of switch gear, current and voltage transformers.