Quantity Surveyor
Civil Construction Center, LLC
Total years of experience :13 years, 4 Months
• Prepared the calculation sheet of quantities using Autodesk QTO for Bill of Quantity
• Established the database of suppliers and subcontractors of different trades
• Delegated and reviewed the tender documents prior to submission
• Raised inquiries to consultants and achieved timely replies through follow-ups.
• Prepared baseline, resource loaded programme and submitted to client for approval
• Acquired the approval of baseline schedule from client
• Tracked and monitored the progress of the project by updating the baseline programme
• Prepared and submitted the daily, weekly and monthly report on time
• Clarified each query which comes from subcontractors and provided the necessary documents
• Prepared the calculation sheet of precast elements for Bill of Quantity
• Prepared the cost sheet of each precast element for pricing
• Prepared the daily production schedule in spreadsheet and entered the elements in the AcctMax, the ERP software used by the entire organization
• Coordinated the project team to prepare the required precast elements and coordinated with the transport team for the timely delivery schedule
• Coordinated the technical team on any revision works and expedited approval of shop drawings for implementation
• Prepared progress update sheet and achieved timely completion of projects
• Managed and secured the site documents in ACONEX, document management system
• Prepared and maintained document logs and register
• Demonstrated effective coordination system among the stakeholders of the project in terms of progress reporting, manpower supplies and monitoring and office and site logistic needs
• Drafted letters, Minutes of Meeting and other correspondences related to the project
• Organized technical and coordination meeting with the subcontractors involved in the project
• Assisted the site manager in quantity take-off for site procurement
• Assisted the site engineers in the preparation of Field Change Request (FCR) and Site Instruction (SI) and helped in the closing of NCR
• Prepared manpower attendance sheet and submitted to HR head office on time
• Prepared daily activity report and sent to head office on time as instructed.
• Prepared Programme of Works and material estimates for Budget Approval
• Supervised and completed government construction projects on time
• Accounted for project expenses, material procurement, manpower resource allocation and manpower salaries and successfully completed the project with honesty and integrity
• Led the survey team in the relocation of boundary lines in the sanitary landfill, the establishment of marine protected area, forest land survey and road surveying works
• Conducted public safety inspection on government and private owned buildings
• Involved in the USAID project on environmental cause by being part of the Technical Working Group working on planning and collaborating with the different stakeholders of the community with the locality.
• Assisted in the review of plans and required documents for the authority approval and issued permits to applicants
On-going Studies
Passed the Civil Engineering Board Examination given by the Professional Regulation Commission Passed the Jr. Geodetic Engineering Board Examination given by the Professional Regulation Commission. Practiced the civil engineering profession from 1996 to present
Graduated with Special Awards in Mathematics Top 5 on the National College Entrance Examination (NCEE). Chess Varsity Player