محمد عبد الواحد, Power Supply Senior Automation Engineer

محمد عبد الواحد

Power Supply Senior Automation Engineer

Orascom Construction Limited - Egypt

البلد
مصر
التعليم
بكالوريوس, كهرباء قوي
الخبرات
11 years, 5 أشهر

مشاركة سيرتي الذاتية

حظر المستخدم


الخبرة العملية

مجموع سنوات الخبرة :11 years, 5 أشهر

Power Supply Senior Automation Engineer في Orascom Construction Limited - Egypt
  • مصر - القاهرة
  • أشغل هذه الوظيفة منذ يوليو 2022

Cairo Metro Line 4 (Power station & Rectifier Station Control System).

* Engineering Work for 43 PLC Panels and 137 Remote RTU Panels.

1- Review and Study Single Line diagram and Specification to prepare IO List for integration with Switchgear and Protection Relays.
2- Build system network using Modbus protocol to read/write data and signals from and to Protection Relays & Remote IOs, and to read/write signals from SCADA.
3- Prepare System Control philosophy.
4- Prepare PLC Panels General Arrangement and Wiring diagram.
5- S7-1500 PLC Programming using Simatic manager and HMI Programming using TIA Portal.
6- Cable list and interconnections cables details between Switchgear and Remote RTU.
7- Prepare FAT documents.

Senior Automation Engineer في Al-KOUT Industrial Projects
  • الكويت - الفحيحيل
  • يناير 2021 إلى يوليو 2022

- AL MUTLA HIGH STAGE-II CHLORINE DIOXIDE PLANT MEW5258.

* Engineering Work for 4 PLC Panels, 28 LCP and DCS.

1- PLC Panels Inputs/Outputs List.
2- Reviewing PLC Panels General Arrangement and Wiring diagram.
3- Cable list and interconnections cables details for full system starting from Instrumentations passing by junction boxes to Marshalling cabinet.
4- Build redundant Modbus Network between PLC Panels and LCPs to DCS.
5- Lead the commissioning of the Automation System with the client.
6- S7-412 H PLC Programming using Simatic manager and HMI Programming using TIA Portal.

* Workshop and Site Work.

1- Supervise on 4 PLC Control panels and 28 LCPs assembly.
2- Supervise on installation of PLC Panel and LCPs.
3- Supervise on Cables layout and termination for PLC Panels, LCPs and JBs
4- Active participation in meeting with main contractor and other Vendors.

Automation Engineer في Al-Fanar Engineering
  • الكويت - حولي
  • أغسطس 2018 إلى يناير 2021

- First Stage SABIYA Gas Turbine to combined Cycle Plant CCGT-1 MEW55 Chlorination system (PLC Panel) Siemens S7 400 Redundant CPU, Redundant Power supply And Redundant Modbus Communication to DCS:

- Supervision on installation of PLC Panel and all wiring termination.
- Finish the commissioning activities on site and finish as built documents.
- Attend the inspection of the system with Clint MEW (Kuwait ministry of Electricity and Water)


- Third Stage SABIYA Gas Turbine to combined Cycle Plant CCGT-3 MEW54 Chlorination system (PLC Panel) Siemens S7 400 Redundant CPU, Redundant Power supply And Redundant Modbus Communication to DCS:

Finish all PLC Panel Engineering Documents and Software.

1- Inputs/Outputs List.
2- PLC Panel General Arrangement and Wiring diagram.
3- PLC Function design specification.
4- SAMA Logic (Control System Logic).
5- Control Panel Load calculation.
6- Cable list and interconnections details.
7- PLC software (Simatic manager).
8- HMI Software (TIA Portal V15.1).
9- Prepare Factory acceptance test (FAT) document and attend it with the client.
10- Finish the commissioning activities on site and finish as built documents.
11- Attend the inspection of the system with Clint MEW (Kuwait ministry of Electricity and Water)

Power Supply Automation Engineer في (IAS) Industrial Automation System
  • مصر - الإسكندرية
  • يونيو 2016 إلى يوليو 2018

- Riyadh Metro Project (Saudi Arabia) Electrical Substations PLC and HMI Software

1- Draw all ACC (Automatic control cubicle) Panels and MC (Marshalling cabinet) Panels using AutoCAD Electrical software.
2- Programming (Schneider Modicon M340) PLC SW using Unity Pro SW.
3- Programming (Schneider HMI GTU) HMI SW using Vijeo Designer SW.
4- Build system network using Modbus protocol to read/write data and signals from and to Protection Relays & Remote IOs, Signals like (Current, voltage, power reading and faults signals).
5- FAT Documentations Prepare.
6- Active participation in Factory Acceptance test in Dammam KSA with the Contractor ALSTOM.

- Nama Factory Project.

1- Create new data Base using SQL Server and connect to SCADA (Vijeo citect).
2- Batching Report saved to SQL Server and export reports to Excel file.
3- Design Pressing Machine PLC and HMI Software using Unity Pro and Vijeo Designer SW.
*Software Used (Unity Pro, Vijeo citect, Vijeo Designer and SQL Server)

- APG Factory

1- Solve old system Communication problem between SCADA (Citect) and 3 PLCs S7300 and S7 400 using Simatic Net Software.
2- Add new workstation and work as a slave for Master Unit.

Instrumentation Engineer في The National Company for Fertilizers & Chemicals (AGROCHEM)
  • مصر - الإسكندرية
  • ديسمبر 2012 إلى يونيو 2016

Shift in charge, leading a team of 3 technicians responsible of all electrical and Instrumentations faults for 3 lines.

- Sulphuric Acid Factory

1- Participated in startup of the factory.
2- Instrument calibration ST3000 Transmitters (Honeywell).
3- Apply modifications on Factory ABB AC800F DCS System by Adding New Screen
(All Factory data in one Screen) using Free Lance 800F Software.
4- Design a new Project (Line 2) PLC Software and Scada system using (Simatic manager Software and Wincc 7.0 software)

- Ammonium Sulfate Factory

1- Participated in construction of the factory (Instrument installation and wiring).
2- Instrument calibration (Endress+Hauser).
3- Apply modification On Factory PLC and SCADA System by Adding New instruments and Screens (Trends Screen - Interlocks Screen - Documents Screen - All Factory Data in one Screen) Using Simatic manager and Wincc 7.0 Software.

- Steam turbine

1- Participated in soft start and safe shutdown of the steam turbine.
2- Apply modification on the old Turbine PLC Software (LG - MasterK 200S) using KGL
Software and HMI (XB50) using XB Builder Software.
3- Design a new Turbine PLC Software and SCADA system using (Simatic manager Software
And Wincc Comfort software)

الخلفية التعليمية

بكالوريوس, كهرباء قوي
  • في كلية الهندسة جامعة الاسكندرية
  • يونيو 2011

Specialties & Skills

اللغات

الانجليزية
متوسط

الهوايات

  • الجري
    المشاركة اكثر من مرة في مارثون جري علي البحر بالاسكندرية