Designation: Electrical Supervisor Feb 2020-Sept 2021
PROJECT: BAB INTEGRATED FACILITIES PROJECT (BIFP-PROJECT), HABSHAN.
CLIENT : ADNOC
Job Responsibility:
Worked in E&I activities of Remote Degassing Stations(RDS)- RDS5, RDS8, RDS9, MINIPAD's WELLHEAD CONTROL PANELS, OFFPAD Wellhead, DEWATERING CONTROL ROOM, 33KV RMU PANELS Installations, 3.3KV MOTOR (PUMP) PANEL Installation, Electrical works of Plant Switchgear Room.
Installation of Control Room Panels, Lighting Installations, Cable Tray, Cable Pulling, Wellhead Control Panels, Solar Panels, Battery Box, Installation of MOVs, Junction Box, Main Distribution Box, Fire and Flame Detectors, Flammable Gas detectors, Different types of Sensors, Temperature Indicator, Pressure Indicator, Label Indicator, Different type of Transmitter, Installation of Pressure Transmitter, Temperature transmitter, Label and Flow transmitter and other measuring instruments.
Installation of 2*4MVA, 33/3.45 KV Power Transformers, 2*2.5MVA, 3.3/0.433KV Transformer in RDS8 and RDS9 Substation, Busbar panels, VRC Motor panel, Disposal Motor Pump Panels, Wealhead control panels, Close Drain Drum and Oil Return Drum Panels installation, Manifold MOVs Main Distribution Board Panels installation, Cable Pulling, Cable Tray, Glanding and termination and panels installation of RDS8 Plant Control Room.
Installation 290 KW Motor for Vapour recovery Compressor (VRC), 330KW Disposal Motor Pump installation, Motor of Close Drain Drum and Oil Return Drum, VRC FIN Fan Motors installation.
Basic Knowledge of Dewatering Separator, Knock Out Drum (KOD), Nitrogen Injection Unit, Nitrogen Receiver, Instrument Air Receiver and Chemical Injection Unit.
To conduct inspections all ongoing activities for electrical installations, to conduct inspections for all electrical material deliveries.
Prepare method statement (MS), Inspection Test Plan (ITP) and Quality Control Procedures (QCP) in coordination with QA/QC senior engineers and Project engineers.
Check the drawings and documents used at site for approvals and compliance with Project Requirements
Prepare daily QA/QC report regarding inspections, material, Non conformance etc. Prepare weekly surveillance reports, non conformance reports and verification of corrective actions. Ensure that all works are carried out as per the ADNOC approved and compliance of corrective action.
Review & approval on the Project Quality Plan (PQP), Project Execution Plan & other Project Procedures documents.
Ability to Read and good Understanding of P&ID drawings and carryout works as per P&ID and Isometric drawings.
Responsible to complete the E&I field works as per approved drawing & method statement.
Ensure the materials used and quality of the work as per approved standard and specifications. Tools & Tackles, Equipment Thirty Party Documents to be maintained.
Assess interference between activities, full time presence at the worksite during the whole duration of work, stay at working sites to follow-up progress of activities, ensure the safety of operations covered with PTW system in respect with ADNOC HSE rules.
Implements the work activities based on the Method of Statement and Task Risk Assessment.
Prepare MIS and other site related documents and report to construction manager.
Ensuring that Project quality Plan and procedures, Performing inspections of installations when advised by construction-in-charges, Monitoring the phases of quality control of work as per specification, Develop and maintain inspection procedures and techniques throughout the construction, pre-commissioning and commissioning stages.
Inspect high & low voltage terminations, cable pulling operations and substations, inspect above and below ground electrical installations, test transformer and switch gear oil, inspect on electrical motors, generators, transformers, switches etc.
- Company industry:
- Oil & Gas
- Job role:
-
Electrical Engineering