acting resident engineer
gulf consult
Total years of experience :44 years, 4 Months
resident engineer as part time in different projects
utility section engineer, following & supervising all works related to utilities excution ( water pipe lines, storm water, treated sewage water pipe lines & sanitary sewers pipe lines .
construction, completion & maintenance of roads, bridges, storm water drainage, sewer & other services for cairo street .
value about 105, 000, 000 kd .
Responsible for the organization, supervision and complete administration of site activities, in accordance with the contract documents, quality standards and good construction practices & determine policy for the supervision, monitor the process of the work and ensure that the project is executed to the complete satisfactory of Owner.
construction of multistory car park for national guard in altahreer camp .
Responsible for the organization, supervision and complete administration of site activities, in accordance with the contract documents, quality standards and good construction practices & determine policy for the supervision, monitor the process of the work and ensure that the project is executed to the complete satisfactory of Owner.
construction of walid &abdulrahman alosaimy center for intensive heart survices in alsabah health area of 16, 300 m2 approximate consisting of basement & seven floors building, project value of about 6, 000, 000 KD
Subscribe to the formulation and preparation of contractual documents for contracts and various agreements and prepare responses to correspondence and claims of Contractors according to the contractual documents and participate in the preparation of Ministry responses and defenses against the various raised issues by Contractors as well as to identify contractual issues disputed and take appropriate action to ensure satisfactory solution for all parties.
Responsible for the organization, supervision and complete administration of site activities, in accordance with the contract documents, quality standards and good construction practices & determine policy for the supervision, monitor the process of the work and ensure that the project is executed to the complete satisfactory of Owner.
Construction of four buildings A, B, C & D, External & internal finishes, All MEP works, Telemetry SCADA system for building A & external site works, project site area is 110, 450m2 inside Ardia waste water treatment plant, project value is 16, 385, 200KD.
Subscribe to the formulation and preparation of contractual documents for contracts and various agreements and prepare responses to correspondence and claims of Contractors according to the contractual documents and participate in the preparation of Ministry responses and defenses against the various raised issues by Contractors as well as to identify contractual issues disputed and take appropriate action to ensure satisfactory solution for all parties.
Responsible for the organization, supervision and complete administration of site activities, in accordance with the contract documents, quality standards and good construction practices & determine policy for the supervision, monitor the process of the work and ensure that the project is executed to the complete satisfactory of Owner.
Construction of Specialty Eye Center in Al-Shaab Area. Project Value of about 3, 020, 000.00 KD
Project consists of 8 typical floors, Basement, Ground floor, Roof floor and Upper roof. Total gross built area is 6400M2 is being constructed on plot of 1010.5 M2 including both Skelton and finish packages with all related Mechanical, Electrical and Medical Works necessary for operation of such project
Subscribe to the formulation and preparation of contractual documents for contracts and various agreements and prepare responses to correspondence and claims of Contractors according to the contractual documents and participate in the preparation of Ministry responses and defenses against the various raised issues by Contractors as well as to identify contractual issues disputed and take appropriate action to ensure satisfactory solution for all parties.
Responsible for the organization, supervision and complete administration of site activities, in accordance with the contract documents, quality standards and good construction practices & determine policy for the supervision, monitor the process of the work and ensure that the project is executed to the complete satisfactory of MPW.
MPW - SE/71
'construction, completion, and maintenance of transfer TSE lines to the artificial lake in UM ALREMAM and northern military campus, project consists of 1400, 1200, 1000, 400, 300, 200 mm dia GRP PIPES OF approximate length 110 kilometers and pipe laying of about 400 meters by nondisruptive method under road crossings in addition to different valve chambers and thrust blocks constructed on pipe routing such as isolation, air, washout, flowmeter valve chambers etc. in addition to construction of Two Administration Buildings of 1200 m² each, T.V. Chamber, small pumping station in Amghara, value of about 17, 000, 000 K.D.
Supervising the construction of 1400, 1200, 1000, 400, 300, 200 mm dia GRP PIPES OF aproximate length 110 kilometers and pipe laying of about 400 meters by nondisruptive method under road crossings in addition to different valve chambers and thrust blocks constructed on pipe routing such as isolaton, air, washout, flowmeter valve chambers etc.
Manufacturers and suppliers of high density polyethelene
pipes for gravity and pressure uses.(for storm water, sanitary, ducting and drainage) networks.
projects technical support and Achieving the company target plans for marketing its products through the local and outside markets
Kuwait Sewerage Renovation Project Phase VI Part B SE-44/05-08 Abraq & South Khaitan Project value of about 9 Million KD.
Management of the execution of the project from mobilization upto handing over to the owner. Renovation about 70KM of Sewerage net work. Microtunnelling and open cut of diameters between 200mm upto 1000mm, 2520 manholes and 1958 house connection.
Construction, Operation & Maintenance of New Mishrif Pump Station, Forcemains and Subhan, South Surra & Fahaheel Interceptors - Contract No. SE/19, contract value of about 42 million KD.
Deputy Project Manager and direct responsible on execution of Force Mains consisting of 38 KM (1400 + 1200mm) Ductle Iron Pipe Lines and Isolation, Air, Washout Valve Chambers. During the Project Manager's absence I am acting as Project Manager and looking after all the project works.
Rehabitation of MPH Hospital, Seventh Group عقد ص/م خ ع /1/ 2000 / 2001-49
Managing and cordinating with several activities subcontractors such as Civil, Electrical, Plumbing, HVAC, Medical gas, Fire Alarm, Nurse calling system and consulting office.
Construction, Operation & Maintenance of New Mishrif Pump Station, Forcemains and Subhan, South Surra & Fahaheel Interceptors - Contract No. SE/19, contract value of about 42 million KD.
Deputy Project Manager and direct responsible on execution of Force Mains consisting of 38 KM (1400 + 1200mm) Ductile Iron Pipe Lines and Isolation, Air, Washout Valve Chambers
Kuwait Sewerage Renovation Project Phase IV Part A-3 SE/32-3/98-99 Rumaithiya & Salmiya Project value of about 6 Million KD.
Management of the execution of the project from mobilization upto handing over to the owner. Renovation aboqut 50KM of Sewerage net work microtunnelling and open cut of diameters between 200mm upto 800mm. 1767 manholes and 1728 house connection.
Construction of International Kuwait Airport Box-culvert (RA/56) - Project Value of about 1, 100, 000 KD.
Management of the execution of the project (Box Culvert) which is composed of 3x2 ms. One vent) 2.5 km. length +350 MS of 1800 RC Pipes and (asphalt, road works, detours, storm water pipe connection).
construction of infrastructure project in AL-Nosairat City project value of about 1, 000, 000 Dollars .
Supervising the construction of a new water, sewerage & telephone networks plus construction of new roads
Construction & Maintenance of Kabad - Sulaibiya road .
Perform works for road crossings, ducts, relocating utilities & construction of fresh water pipe line.
Hawalli water maintenance center .
a)Managing the center staff comprising of (Engineers, Assistant Engineers, Supervisors, Technicians, Clerk & Drivers) the center is serving differnet areas of about 250, 000 population through a water network of about 1, 000 km length of different diameter pipes between 80mm to 1600mm. This center is responsible on all the maintenance works needed to keep the water network in a good condition and solving all the problems that arise or appear through the operation.
b) Managing and training of Assistant Engineers who are studying in water & electricity training institute for about two months yearly.
c) Member of different committes such as:-
- Committees of studying tenders
- Committees of handing over different projects
- Committees of studying & checking problems that arise because of water affect.
Emergency maintenance & repairing of water networks & its accessories project.
Supervising all the works needed to maintain the water networks in a good working condition (Repairing pipes, different types, sluice valves, washouts, air valves fittings etc., and all the components of the network.
(Water Emergency Plan) project.
Supervising excution of fixing & installation of fire hydrants (pillar type) & filling points, pressure reducing valves, & water flowmeters & dall tubes in most places in Kuwait in addition to the construction of all types of chambers. Preparing Daily, Weekly Monthly Reports & Payments.
Construction of Water networks in Al Fintas Area.
Supervising the construction of fresh & brackish water networks consistings of D.I & asbestos pipes all types of valves, fittings & chambers, managing staff of Junior Engineers, Supervisors & Surveyors, preparing daily, weekly, & monthly reports & payments certificates.
Water distribution complex in Doha.
Supervising the construction of different elements of civil works such as (buildings, landscape, underground, reinforced concrete reservoirs, road works.
Construction of 50 Million Gallon water reservoir in Mina Abdullah.
Supervising the construction of 50 million gallon reinforced concrete underground reservoir and the surrounding pipe lines including the inlet & outlet, washouts chambers beside the construction of small building nearby.
My Highest educational qualification is the B.Sc. Degree in Civil Engineering Structural Section with general grade (Very Good) and the Project is Reinforced Concrete Structures with a grade of (Very Good)