- Project engineer (Mechanical works & piping) responsible of MEP works for 7 pumping stations, 3 fire fighting pumps room, fire fighting including & not limit to fire hydrant, fire hose reels, fire cabinets, sprinkler system, fire pipes, HVAC system for all substations related to our scope & all ventilation system (63 fans including air monitoring system) & firefighting system for tunnels/underpasses. Project consists of 3 tunnels, underpasses, bridges & flyover, 5nos. Substations & 7nos. pumping stations.
- Project Engineer for design, installation and follow well head & piping works for deep injection wells - TSE application, drilling deep wells up to 400 m and 50 m including installation of casing, cement and all related works.
- Responsible for water supply system & drainage system for all tunnels/ underpasses.
- Responsible for technical submission, material submittals, shop drawings, follow with suppliers for all valves (GV, BFV, AV, SV, DI piping…) required for all services in the project.
- Witness FATs.
Al Jaber & Partners Company: Doha, Qatar summer 2008 - present
I took the responsibility of organizing the works, planning activities, teaching the staffs, and representing C.M during meetings. On the other hand, I am in charge for all the site activities.
- Site Engineer for Storm water, responsibility of organizing the works, planning activities, teaching the staffs, excavation, pipe laying, backfilling, fixing Manholes, testing and commissioning.
May/2012 - Present
Client: ASHGHAL: Total Contract Amount: 2, 333, 858, 204.60 QR = 640, 000, 000 Millions $.
Project title: Construction and upgrading of infrastructure of Al muntazah street extension - Package 13.
- Project engineer (Mechanical works & piping) responsible of MEP works for 7 pumping stations, 3 fire fighting pumps room, fire fighting including & not limit to fire hydrant, fire hose reels, fire cabinets, sprinkler system, fire pipes, HVAC system for all substations related to our scope & all ventilation system (63 fans including air monitoring system) & firefighting system for tunnels/underpasses. Project consists of 3 tunnels, underpasses, bridges & flyover, 5nos. Substations & 7nos. pumping stations.
- Project Engineer for design, installation and follow well head & piping works for deep injection wells - TSE application, drilling deep wells up to 400 m and 50 m including installation of casing, cement and all related works.
- Responsible for water supply system & drainage system for all tunnels/ underpasses.
- Responsible for technical submission, material submittals, shop drawings, follow with suppliers for all valves (GV, BFV, AV, SV, DI piping ) required for all services in the project.
- Witness FATs.
Common responsibilities
- Perform installation & alignment of equipments; follow work at sites and inspections for sleeves and openings to ensure that work done as per the approved drawings.
- Responsible for subcontractors, coordination, wok at site, drawings, reviews submittal
Provide technical support and supervision for Construction team. Provide guidance to the Foreman's and measure the daily production.
- Review records and documents for completeness and compliance with the requirements; assure good documentation practices.
- Review of all types of Drawings and shop drawings (Mechanical, Civil, Electrical, Instrumentation )
- Mechanical team representative and coordinator in Design coordination technical meetings with the consultant, the client, subcontractor and local authorities KAHRAMAA and ASHGHAL, Qtel.
- Representative of the company for Environment Ministry and Civil Defense to follow the submittals and get approval.
- Prepare & review subcontractor payment.
- Prepare & review subcontractor's agreement.
- Responsible for more than 3 subcontractors.
- Follow materials delivery & shipments.
- Logistic Manager: Responsible about all stores for site work (design the stores, Construction )
- Good ability to follow up teams on ground. Good ability to Handle stress and Overtime
- Receiving material (more that 20 tons and have the ability how to use the crane) and checking the quality and follow with consultant to get approval.
- Performed many courses in safety requirements, precautions & risks.
Training earned earlier:
• Project management (PMBOK 4th edition)
• Install, inspection, maintenance & commissioning works for hydraulic actuators valves. (Certified)
• Understanding pumps - sizing, selection and applications.
• Leed Drainage & Sustainable Pipe Support.
• Daikin VRV Solutions and Green Building Design.
• Different aspects of efficient heat transfer technology, solar heating and solar cooling.
• Overview & application of green building practices in Qatar, Variable speed drive chillers, Fundamentals of insulation green buildings, VRF system - selection & design, Passive fire protection system, Environmental awareness training program, chemical safety training, health & welfare training program.
• ASHRAE 90.1 Standard - Past, Present and Future.
• Assessing Building Energy Performance: From Principles to Practice.
• Attendance of CRC conference for ASHRAE @ Sri Lanka dated 28.09.12.
Other Qualifications
Mar/2011 - May/2012
Client: Qatar Petroleum: Total Contract Amount: 800, 000, 000 QR = 220 Millions $.
- Site engineer responsible of MEP works for pump station (3 pumps 107.5l/s) and 2nos. Qtel building for Mesaid project Doha, Qatar, prepares submittals, shop drawings, coordinate with sub-contractor.
- Reporting progress and concerns to the Construction Manager, Project Manager.
Engineering studies: ADNAN ALAYAN Fall 2007
Assistant Engineer-Internship
- Planned and designed the HVAC system, plumbing, draining, piping size, and pumps.
Engineering Services Group - YORK (KUWEIT) Summer 2007
Assistant Engineer-Internship
- planned and designed the HVAC system: - Heat and cooling load calculation
- Duct and pipe measurements
- Equipment and duct location
- On-site inspection
• Final year project, GREEN CITY, the objective of this project is to reduce the emission of CO2 in a 54 000 resident town in south Lebanon named Nabatieh. The reason of the study consists to evaluate the actual emission situation named base case and propose different alternatives to minimize the energy consumption (using the renewable energy, performed the energy efficiency for building .) in order to achieve the international standard in CO2 emission.
• Plumbing: calculating water supply system (cold & hot) system FU, drain system, vent, and rain water.
Professional Experience
GHADDAR GROUP Summer 2006
Assistant Engineer-Internship
- Verified the assembly of the generators.
Tested and maintained the generator.