Lead HSE Engineer
Target Engineering Construction
مجموع سنوات الخبرة :17 years, 11 أشهر
October 2016 to March 2023 EMDAD/INTERGULF General Contracting LLC, UAE. as HSE ENGINEER/Sr. SAFETY OFFICER/SAFETY OFFICER.
Efficiently Working as HSE Engineer in EMDAD SERVICES LLC, ABUDHABI.
Project Title: Static Equipment Maintenance Services for Poly Olefins Units-Borouge-2-TA.
Client: ADNOC POLYMER COMPANY(BOROUGE)-RUWAIS.
Duration: DECEMBER 2022 to MARCH 2023.
Scope of Works: Servicing & Inspection of Heat Exchangers, U tube exchangers, Fixed tube bundle, Vessels, Prepoly Reactor, Loop Reactor, Gas Phase Reactors, Column, Tower, Line Cleaning, Hydrotesting, Blinding & De Blinding, Piping Fabrication & Installation, Removal & Refixing of Control valves and PSV’s, Manual valves, Silos Filters & Strainers cleaning.
Efficiently Worked as HSE Engineer in EMDAD INTERGULF LLC, ABUDHABI.
Project Title: INDUSTRIAL CIVIL WORKS AT DAS ISLAND PACKAGE-A, C &D.
Client: ADNOC OFFSHORE(ADMA) @ DAS ISLAND.
Duration: September 2018 to June 2022.
Scope of Works: Removal and Replacement of deteriorated existing concrete foundations and cable trench cover slabs in various process plants. Interlocking tiles fixing inside the plants, containment cells modifications, earth works for installation of additional cable ducts and cable trench pit repair works.
Project Title: CATALYST REPLACEMENT JOB.
Client: ADNOC SOUR GAS (AL HOSN) @ SHAH FIELD.
Duration: April 2018 to May 2018.
Project Title: ASAB PLANTS 0, 1&2 2018 TURNAROUND
Client: ADNOC GAS PROCESSING (GASCO) @ ASAB
Duration: Feb 2018 to March 2018.
Scope of Works: Replacement of MOV, PRV valves, Spading, De-Spading’s, Catalyst
Replacements, Fin Fan Coolers modifications and hydro test, Hot works.
Project Title: ADCO OFF STREAM INSPECTION PROJECT (JC-1777).
Client: ADNOC ONSHORE (ADCO) @ HABSHAN
Duration: Oct 2017 to Jan 2018.
Scope of Work: Removal of sludge, internals and cleaning of GAS separators at Compression stations 1 to 4 and RMS’s - 1, 2, 3 and 6.
Project Title: INTIGRATED OF CIVIL WORKS. (CON-PAC-058-2013/LCE#1DS)
Client: ADNOC LNG (ADGAS) @ DAS ISLAND.
Duration: NOV 2016 to June 2017
Scope of Project: Removal and Replacement of deteriorated existing concrete lining of impounding basin (LPG/LNG pit) plant 27, Installation of temporary support and concrete repair works in Valve chamber area at pipe rack # 05, Sun shelter for crane parking, Pasco paving’s and E & I works.
Notable Accomplishments
Successfully achieved and completed ADNOC GAS PROCESSING ASAB plants Turn Around shutdown with ZERO ACCIDENT.
Got appreciation Certification from GASCO SHUT DOWN MANAGER for Best HSE Performance during Turn around.
Scope of Work: Removal and installation of Carbon Blocks inside Furnace, Refractory works for
Furnace main production lines, Stove repair modification works, Electrical panels installations, and cable
laying’s inside cable tunnels, main conveyor mechanical and electrical works
ASAB Full Field Development Project (M.E.I PACKAGE -2, WELL TIE-INs).
Client: Abu Dhabi Company for Onshore Oil Operation (ADCO)
Notable Accomplishments:
➢ Installation of process Reactors, Centrifuges, Distillation columns, Solvent and Storage
Tanks, Hypochlorite treatment plant, STP and Boiler Chimney in Production Blocks I & II.
➢ Successfully Installed of Fire Hydrant system, Sprinklers, Smoke and Fire detectors.
➢ Demonstrated excellence in implementing the merit system SAFE EMPLOYEE OF THE MONTH
as a motivational measure for the employee.
➢ Introduced daily base Inspection check list for crane and Equipment’s.
➢ Introduced daily base PB-I & II, Generator room inspections and close outs.
➢ Introduced Safety Committee Meetings with HSE committee members on monthly basis
courses: IOSH Managing Safely, Abu Dhabi, U.A.E.