Submitting more applications increases your chances of landing a job.

Here’s how busy the average job seeker was last month:

Opportunities viewed

Applications submitted

Keep exploring and applying to maximize your chances!

Looking for employers with a proven track record of hiring women?

Click here to explore opportunities now!
We Value Your Feedback

You are invited to participate in a survey designed to help researchers understand how best to match workers to the types of jobs they are searching for

Would You Be Likely to Participate?

If selected, we will contact you via email with further instructions and details about your participation.

You will receive a $7 payout for answering the survey.


User unblocked successfully
Peyman Tahermoghaddas, Manager of Project Controls

Peyman Tahermoghaddas

Manager of Project Controls·Zolal

Canada

Bachelor's degree,

Work experience

Total years of experience: 30 years, 2 months

Manager of Project Controls

October 2010 - Present

Zolal

Iran

October 2010 - Present

In my current position I am directly responsible to:
• Analyze project documents including Project Execution Plan, and technical drawings, to prepare activity networks, and to prepare detailed work schedules and manpower histograms
• Manage resource requirements and business needs for projects, anticipate problems; develop innovative solutions and ensure solutions are consistent with organizational objectives
• Update schedules, and perform critical path analysis
• Optimize current scheduling management process, and establish the major scheduling warning system

Company industry:
Oil & Gas
Job role:
Management

Project Controls Manager

February 2009 - August 2010

TOP Engineering Company

Iran

February 2009 - August 2010

o As the project controls manger on the client side, led a team of 8 qualified planners and schedulers. Directed all project control related activities for the $2 billion U.S. dollars “Gas Field Development Project” located at Kish island, south of Iran.
The project consisted of about 40 subprojects ranged from infrastructures, and facilities, to industrial subprojects. Major subprojects include clusters facilities preparation project, a 90km of onshore and 10km of offshore pipe line project, one power plant project, a water intake and a water treatment project, waste water treatment project, a 120km highways project, and the gas refinery project as well as other subprojects “mostly as EPCC or PC projects” to subcontractors. The project was designed to produce 970 million ft3/day of gas in phase one.
o Directed schedule development activities, schedule maintenance techniques, project monitoring, change impact identification methods, and recovery plan development actions.
o Directed cost and resource estimations, and controlled budgeted cost reports.
o Provided guidance, and offered innovative solutions for generally non routine cost and planning problems.
o Interrogated schedules submitted by EPC contractors to ensure conformity with agreed contract milestones.
o Reviewed reports prepared by contractors, and integrated them into higher level of reports.
o Analyzed base-plans and forecast schedules.
o Examined underlying logic links and verified correctness together with field managers.
o Supported project/ program organizational and administrative activities.
o Overview document control procedures.

Company industry:
Oil & Gas
Job role:
Management

Field Planner

December 2006 - December 2008

Stone & Webster, Kingdom of Saudi Arabia, YANBU

Yanbu, Saudi Arabia

December 2006 - December 2008

o Developed detailed schedules for construction, pre-commissioning and commissioning phases.
o Loaded schedules with resources according to the BOM, and contract pay item lines.
o Reviewed and approved subcontractors’ detailed schedules.
o Integrated subcontractors detailed schedules into the overall project master schedule, and provided frequent updates to the master plan, and prepared progress reports.
o Monitored contractor progress, and developed and implemented recovery plans as required.
o Prepared project weekly and monthly progress reports.
o Constantly documented all delay evidences, and evaluated EOT, Extension-Of-Time, requests.

Company industry:
Oil & Gas
Job role:
Engineering

Planning Engineer

May 2006 - December 2006

Shaw Stone & Webster Canada

Canada

May 2006 - December 2006

o Analyzed progress data, and reviewed project schedule.
o Frequently updated project statues for the entire engineering, procurement and construction departments in the YANBU Petrochemical Complex to make sure that the project will be finished on time and within budget.
o Produced, and documented schedule forecasts, and reported results to the management.

Company industry:
Oil & Gas
Job role:
Support Services

Project coordinator

May 2003 - May 2005

TISACO Engineering Services, Canada

Canada

May 2003 - May 2005

o Managed coordination, and provided services for a 20hec hydroponics greenhouse project on an EPC / turnkey basis, as a “Design-then-Build Project”, for an overseas client.
o Provided cost engineering services, and assisted local Canadian company to prepare and finalize her proposal for the $ 28, 000, 000 project in accordance with client standards.
o Developed detailed construction schedules for all local subcontractors, and prepared master EPC schedule for all phases of the project.

Company industry:
General Engineering Consultancy
Job role:
Management

Project Scheduler

May 2003 - May 2005

Maraghe Pulp and Paper Company, Iran

Iran

May 2003 - May 2005

o Prepared Project Milestone Plan and work breakdown structure.
o Detailed project main plan in 2500+ activities in coordination with technical teams.
o Coordinated 10+ major subcontractors, reviewed their schedules, and kept them on track.

Company industry:
General Engineering Consultancy
Job role:
Support Services

Project Scheduler

May 2002 - May 2003

Heavy Industries Organization, Iran

Iran

May 2002 - May 2003

o Managed the construction phase of 5 industrial plants in an industrial complex by setting out priorities, and allocating resources across all projects.
o Prepared weekly job orders, monitored performance, analyzed progress, calculated earned values, identified variances and reported to major stockholders.

Company industry:
Management Consulting
Job role:
Management

Field Engineer/ Technical office Assistant

May 1997 - May 2000

Tabriz Construction and Development Company, Iran

Iran

May 1997 - May 2000

o Scheduled, and supervised numerous field subcontractors for an EPC project to establish a 200, 000m2 residential and commercial complex.
o Supervised overall generation of monthly invoices.
o Effectively assisted planning team to prepare realistic field job orders.

Company industry:
Construction & Building
Job role:
Engineering

Field Engineer / Project Scheduler

May 1992 - May 1996

SAB Construction Company, Iran

Iran

May 1992 - May 1996

o Scheduled, monitored and reported progress on an 187km pipeline project to establish a 5m3/sec water distribution system to supply water for major petrochemical plants and some populated cities.
o Analyzed project progress, identified delay causes, and provided mitigation and recovery plans.
o Prepared progress tracking reports, and controlling charts for management’s review.

Company industry:
Construction & Building
Job role:
Support Services

Education

Zolal

October 1994

October 1994

Bachelor's degree,

Iran

Tabriz University

September 1984

September 1984

Bachelor's degree, BSc. in Civil Engineering

Iran

GPA (percentage): 87%

GPA (percentage): 87%

Skills

Civil Engineering
Expert
Civil Engineering
Expert
Build Engineering
Expert
Build Engineering
Expert
Proposal Coordination
Expert
Proposal Coordination
Expert
Managed Services
Expert
Managed Services
Expert
Schedule Planning
Expert
Schedule Planning
Expert
Planning and Scheduling
Expert
Planning and Scheduling
Expert
Construction Field Engineer
Intermediate
Construction Field Engineer
Intermediate
Civil Engineering
Expert
Civil Engineering
Expert
Build Engineering
Expert
Build Engineering
Expert
Proposal Coordination
Expert
Proposal Coordination
Expert
Managed Services
Expert
Managed Services
Expert
Schedule Planning
Expert
Schedule Planning
Expert

Languages

English
Expert
Arabic
Beginner
Turkish
Expert

Training and Certifications

Certifications
N/A
SAB Construction Co.
Apr 1993 - Jul 1993