Providing Management consultancy services on construction of ( Hospital, School, administration buildings and Recreation facilities construction )
Responsible for review of approval of Project Baseline for several projects.
Analysis of claims and approval of the same in coordination with Client representative.
Trend analysis, reporting and monitoring contractor progress.
Advice on project current progress and Project recovery plan and revised program approvals.
Recording Project Progress and official correspondences related to planning and scheduling issues.
Certified Planning and scheduling professional from AACEI
Over all more than 10 years of experience in construction Industry with exposure to diversified works and work environment, both as planner and Civil project engineer ( 7 year in Dubai UAE ).
Well understanding of project, scope, Stakeholder concerns, contractor’s responsibility and how to achieve project objectives and goals.
Proficient in Primavera Project management 6.8.2, Primavera 3.1 and Microsoft project.
Develop Project Plan (CPM), Work breakdown structure (Schedule of Works).
Resource and cost loading for earned value management. Cash Flow projection for Engineering, Material & Construction Activities.
Engineering and material procurement Schedule.
Monthly and Weekly Reports and management meeting.
Delay and disruption analysis and its impact on schedule.
Coordination with manager and project engineer, sub-contractors and consultant.
Review Subcontractors program and support in delivering.
Lead Project Team in delivering schedule commitment, identifying critical areas, suggesting and implementing recovery plans.
Excellent communication and computer skills in all respect with basic hand on SQL, SQL server and Oracle Server related to Primavera.
Well versed in Microsoft Soft office VB applications.
Created and customized various “atomized Engineering” Logs & application using excel and Access, for live update and daily reporting.
Prepared contractors construction resource loaded program using CPM technique with more than 3500 activities and numerous sub projects for Desalination plant, as well as power plant e ach. (civil works) (At M Station Jebel Ali, Dubai.)
Estimation of required man power in life cycle of project using resource Loaded program. Preparation of Manpower histogram, S-curves and Project cash flow (Cost Loading).
Revisions & recovery schedule & weekly Progress meetings with main contractor.
Frequent site visit and updates, review, revision
Preparation of schedule on primavera for Tendering as well as for on site implementation.
Comparison of planned and actual manpower, and targeted date and actual comparison
Identifying reason of delays and its impact on base line.
Material, drawings and other Deliverables Schedule
Execution of civil work for Air Traffic Control (ATC) tower and allied buildings.
Main Runway, Taxi track, Drain works.
Hanger works and extension of run way.
Execution of overall civil work and installation of 100 TPH crusher and batch mix plant.
Setting out works and land surveying
Preparation of bar bending schedule.
Quality Control