Work Experience

Total years of experience :16 years, 3 Months

Senior Planning Engineer at Elegancia Landscape - A member of Estithmar Holding
  • Qatar - Doha
  • My current job since January 2020

Project Handled:
PROJECT # 9 Softscape, Irrigation & Hardscape at 12 Villas at Legtaifiya
PROJECT # 8 Softscape, Irrigation, Hardscape & Water Feature at Two Villas Compound at Lusail Palace
PROJECT # 7 Landscaping Works at The NED Hotel - Doha City Club
PROJECT # 6 Landscaping Works for Mr. Jabir Hassan Al Hossain Villa
PROJECT # 5 Landscaping Works for Sheik Nasser Al Khelaifi Villa
PROJECT # 4 Supply and Planting of Trees & Irrigation works around Lusail Palace at Al-Daayen
PROJECT # 3 Design and Build of Al-Daayen Project (Irrigation Network and Softscape)
PROJECT # 2 Hamad International Airport Terminal Expansion Project (Design and Build of Greenhouse
Nursery, Terminal Expansion Irrigation and Softscape)
PROJECT # 1 Design and Build of Lusail Palaces (Water Feature, Hardscape, Irrigation and Softscape)
• Schedules, plans, and oversees the entire program of work.
• Plans, organizes, and coordinates planning activities.
• Selects the most appropriate techniques and logical sequence of activities to complete project scope.
• Inputs the work breakdown structure information in means to assess an accurate forecast on time, resources, and cash flow of the project.
• Maintains and updates technical records, prepares technical reports, helps in generating data for inputs to budgets, improvement in maintenance methods/procedures, equipment replacement, etc.
• Determines appropriate logistics solution in managing resources.
• Sets up alerts for all important contractual and milestone dates.
• Prepares cash flow, charts, and histograms on planning projects.
• Verifies critical path and interfaces between design/ engineering/ procurement / execution.
• Monitors progress periodically and compares it with the baseline planning.
• Updates the schedule based on inputs received from project team.
• Prepares the Weekly and Monthly Progress reports.
• Prepares the monthly Labor histograms.
• Accumulates, collects, and analyses data and information required for planning.

Senior Planning Engineer at Urbacon Trading and Contracting
  • Qatar - Doha
  • March 2019 to January 2020

Project Handled:
PROJECT # 4 Civil Work and expansion of existing Yard in Villa 14 &15 at The Pearl
PROJECT # 3 Fit-out Works Com18 Lusail
PROJECT # 2 Design and Construction of VVIP Villa at The Pearl
PROJECT # 1 Design and Construction of Duhail Palace
• Schedules, plans, and oversees the entire program of work.
• Plans, organizes, and coordinates planning activities.
• Selects the most appropriate techniques and logical sequence of activities to complete project scope.
• Inputs the work breakdown structure information in means to assess an accurate forecast on time, resources, and cash flow of the project.
• Maintains and updates technical records, prepares technical reports, helps in generating data for inputs to budgets, improvement in maintenance methods/procedures, equipment replacement, etc.
• Determines appropriate logistics solution in managing resources.
• Sets up alerts for all important contractual and milestone dates.
• Prepares cash flow, charts, and histograms on planning projects.
• Verifies critical path and interfaces between design/ engineering/ procurement / execution.
• Monitors progress periodically and compares it with the baseline planning.
• Updates the schedule based on inputs received from project team.
• Prepares the Weekly and Monthly Progress reports.
• Prepares the monthly Labor histograms.
• Accumulates, collects, and analyses data and information required for planning.

Planning Engineer at Man Enterprise Qatar W.L.L.
  • Qatar - Doha
  • May 2012 to March 2019

Projects Handled:
Project#6 : Viva Bahriya Package Towers 14&15 Projects
Project#5 : Marina Res10 Towers Project - Lusail
Project#4 : Qatar Early Warning Radar Project (Building and Road Works) - Al Khor
Project#3 : Paloma Restaurant & Staff Accomodation Works Project - Intercontinental Katara
Project#2 : Umm Obairiyah Complex Project
Project#1 : West 4-Storey Car Park Project - Education City
• Tracking and following up the actual progress on site
• Updating the project execution plan to reflect the actual progress and prepare recovery plans & lookahead plans where necessary
• Prepare the Weekly & Monthly Progress reports
• To manage the project, including planning, organizing and directing all activities concerned with the design and construction of the Projects.
• Prepare written reports and applications; Progress reporting.
• Schedule, plan and oversee the entire program of work.
• Anticipating demands in terms of labor, materials, equipment and technical challenges.
• Participate in team meetings.
• Gathers and evaluates data for various planning duties.
• Prepares and assembles maps, tables, charts, and reports on planning projects.
• Reporting to the Project Manager for any foreseen potential delay event of the Project.
• Highlight / resolve any foreseen constraint of the Project
• Involve in preparing the Baseline schedule and Planning Package of the Project
• Involve in preparing the Claims for Extension of Time of the Project

Project QS Engineer at Bestem Construction Private Limited
  • Singapore
  • March 2011 to April 2012

• To manage the project, including planning, organizing and directing all activities concerned with the design and construction of the Projects.
• Coordinate with the project team to efficiently address design and construction issues to maintain the schedule
• Supervises and coordinates all workers involved in the project.
• Gives input on various architectural designs and proposed construction methods.
• Perform quantity surveying for interior works and civil works
• Evaluation of claims & etc.
• Review of contract documents and contractual claims submitted by external parties
• Review quotations and progress billing

Project QS Engineer at MAN Enterprise Qatar W.L.L.
  • Qatar - Doha
  • January 2009 to February 2011

• Responsible for site measurement, preparation of variation order, progress and final claims as well as sub-contractor’s payment certification
• Responsible for the preparation of progress reports, claims, variation orders, monitoring of project cost control effectively and finalization of accounts.
• Confirm the adaptability of materials and equipment to specific application.
• Initiate and coordinate with testing agencies.
• Follow-up the company internal claims from site against applications, materials and equipment’s performance.
• Prepare submittals with the Project Manager’s coordination.

Site Engineer at Formtech Builders Corporation
  • Philippines
  • February 2008 to December 2009

• Checking the Progress of the Project
• Coordinate with Supervisors, Subcontractors and Suppliers,
• Explain the Works as per the drawing to sub-ordinates.
• Maintain statistical data and files.
• Review the project specifications, amendments and drawings in their entirety.
• Ensure compliance to applicable Specifications and drawings of materials proposed for the project.
• Make sufficient daily inspections to ensure that all workmanship and materials during the construction of the Project are in strict compliance with the plans and Specifications.

Education

Bachelor's degree, Civil Engineering
  • at Laguna State Polytechnic University
  • April 2007

Specialties & Skills

AutoCAD
Microsoft Outlook
Microsoft Excel
Microsoft Word
Primavera P6
MS Office in Excel
MS Office in Outlook
AutoCAD
MS Office in PowerPoint
MS Office in Word
Primavera P6

Languages

English
Intermediate

Memberships

Philippine Institute of Civil Engineer
  • Member
  • February 2008

Training and Certifications

Construction Management : Reading Drawings & Specification (Certificate)
Date Attended:
August 2022
Construction Management : Safety & Health (Certificate)
Date Attended:
August 2022
Excel Creating a Basic Dashboard (Certificate)
Date Attended:
August 2022
Advanced Primavera P6 (Certificate)
Date Attended:
August 2022
Construction Management : Planning and Scheduling (Certificate)
Date Attended:
July 2022
Excel Essential Training (Office 365/Microsoft 365) (Certificate)
Date Attended:
July 2022
Primavera P6 Essential Training (Certificate)
Date Attended:
July 2022
Time Matters, Programmes, Extensions and Issues of Delay (Training)
Training Institute:
Quantum Global Solutions
Date Attended:
June 2016
Duration:
3 hours
Effect, Cause, Liability – Extension of Time Claim (Training)
Training Institute:
Quantum Global Solutions
Date Attended:
April 2017
Duration:
3 hours
Preparation of Claim for Extension of Time (A practical approach within Construction Contracts) (Training)
Training Institute:
Quantum Global Solutions
Date Attended:
November 2017
Duration:
3 hours
Qatar Contracts Procedure (Training)
Training Institute:
Quantum Global Solutions
Date Attended:
March 2018
Duration:
3 hours
The Society of Construction Law (SCL) Delay and Disruption Protocol and its relevance in Qatar (Training)
Training Institute:
Quantum Global Solutions
Date Attended:
February 2018
Duration:
3 hours
Asphalt Pavement Thickness Design & Asphalt Mix Design using Marshall and Superpave Mix Design (Training)
Training Institute:
Filipino Association of Materials Engineers
Date Attended:
March 2017
Duration:
8 hours
The Employer’s and Project Management Consultancy’s Hidden Agenda (Training)
Training Institute:
Quantum Global Solutions
Date Attended:
April 2017
Duration:
3 hours
Simplified Plumbing Code-Design and Installation (Revised NPC) (Training)
Training Institute:
Philippine Society of Mechanical Engineers
Date Attended:
May 2017
Duration:
8 hours