Senior Planning Engineer
Dorsch Gruppe
Total years of experience :20 years, 5 Months
, Abu Dhabi
* Providing Project Management and Consultancy services for
Projects in Design & Construction for Infrastructure, Buildings and
Landscaping works.
* Monitoring and Control of Design & Construction supervision
projects for Municipal Infrastructure Works.
* Determination of Contract Time Extensions using Time Impact
Analysis Methods.
* Preparation and Forecasting Project Progress and Cash Flow
Estimates for Budgeting & monitoring.
* Assistance for Technical Evaluation for Tender Projects.
Projects Handled:
* Supervision Consultancy for Construction, Completion &
Maintenance of 410 Villas at Al Marfa
o Client - Musanada/ Abu Dhabi Housing Authority (ADHA)
o Budget - AED 1500 Million
* Construction Management for Design and Build of ADIA PIDS
o Client - Abu Dhabi Airports Company (ADAC)
o Budget - AED 100 Million
* Design Consultancy Services for Emergency & Public Safety
Center, Contract 7010
o Client - Hill International Inc./ Abu Dhabi National Oil
Company (ADNOC)
o Budget - AED 100 Million
* Supervision Consultancy Services for Abu Dhabi Municipality
o Client - Abu Dhabi Municipality (ADM)
o Budget - AED 500 Million
, Emirates Aluminium
(EMAL) Phase 2 Project, Abu Dhabi
Turnkey - Green Anode Plant & Butts Crushing
* Contract Value: EUR 100 Million
* Client: Emirates Aluminium (EMAL)
* EPCM: SNC Lavalin International Inc.
* Engineering, Supply & Installation of a Green Anode Plant which includes
o Plant Equipment’s - Vibro Compactors, Bucket Elevators, Apron/ Belt Conveyors, Vertical Mill,
Anode Crusher, Liquid Pitch Tank, Pumps, Silo’s, Power & Free Chain Drives
o Steel Structure - 3, 000 Tons for Green Anode Plant, Butts Crushing Bldg & Conveyor Str.
o Piping Installation - 15, 000 Inch-dia Utility & Process lines
o Civil & Electrical Works - 2000 CuM Concrete and 90, 000 m Cable laying
Major Responsibilities:
As a Sr. Planning Engineer, responsible for preparation and submission of Overall Project Baseline Program
and accountable for the monitoring and Control of the Project. Further review and monitoring of Subcontractors
Schedule covering various Discipline works including Mechanical Equipment’s, Piping, Electrical Works, Civil &
Structural Steel, Fire Fighting & HVAC Works and liaising Coordination among all
Key Accomplishments:
* Prepared micro detailed schedule for Delayed Areas for better monitoring and control
* Arranged for Site Coordination meetings to avoid interruptions among various packages
In-charge as Turnaround
In-charge for Operation & maintenance of 13 MW captive power plant including heat recovery systems.
* Responsible for carrying out planning, overhaul on HFO based medium speed engines.
* Corrective & Preventive maintenance of engine auxiliaries like pumps, reciprocating compressors,
centrifuges, fin fan coolers, heat exchangers, WHR boilers, and refrigeration machines
In-charge for Project planning of Piping & Equipment erection in WIP project worth approx. US $ 3 Million.
* Preparation and tracking of project plan on Primavera.
Page 4 | 4
Project Handled: BARC - SS/MS/GI Piping, Equipment and Structural Steel works at Radioactive Waste
Immobilization Plant - Kalpakkam
Client: Bhabha Atomic Research Center, Department of Atomic Energy, India
,
courses: Certified Project Management Professional (PMP), Project Management Institute, USA