Soumya Chandrasekaran, Senior Planning Engineer

Soumya Chandrasekaran

Senior Planning Engineer

CDM Smith

Location
Qatar
Education
Bachelor's degree, Civil Engineering
Experience
6 years, 9 Months

Share My Profile

Block User


Work Experience

Total years of experience :6 years, 9 Months

Senior Planning Engineer at CDM Smith
  • Qatar - Doha
  • My current job since May 2023

Project : P043 - Link roads adjacent to Al Khor Expressway Project value : 691 million QAR Client : Ashghal
•Respond to contractor claims, perform forensic schedule analysis, assign cause & effect or effect & cause, prepare impact analysis, assess compensability, and prepare recommendation report.
•Respond to and quantify delay event notifications.
•Develop and establish project control reporting.
•Review contractor schedules, validate progress, revise logic to conform to out-of-sequence progress.
•Present progress status update in review meetings.
•Review requests for variations, establish time impact.
•Analyze delays using float paths, propose recovery measures, record concurrent delays.

Planning and Cost Engineer at Keo international consultants
  • United Arab Emirates
  • April 2021 to September 2022

Project : TSE Lagoons Project value : 766 million QAR Client : Ashghal
•Develop and establish project control reporting
•Review contractor schedules, validate progress, revise logic to conform to out-of-sequence progress.
•Present progress status update in review meetings.
•Review requests for variations, establish time impact.
•Analyze delays using float paths, propose recovery measures, record concurrent delays.
•Respond to and quantify delay event notifications.
•Respond to contractor claims, perform forensic schedule analysis, assign cause & effect or effect & cause, prepare impact analysis, assess compensability, and prepare recommendation report.

Planning Engineer at CDM Smith
  • United Arab Emirates
  • April 2017 to July 2017

Programme : Flood Protection Scheme The Flood Protection Scheme was undertaken by Ashghal to reduce or eliminate storm water flooding affecting Doha. The fast-track projects in this programme addressed individual "hotspots" in various locations in Doha by collecting and managing surface water run-off. CDM Smith was appointed as the programme manager. Client : Ashghal
•Develop and establish project control reporting.
•Maintain a correspondence register required to review Claims.
•Review contractor schedules.
•Analyze delays, propose recovery measures.
•Validate and verify contractor progress data.
•Present progress status update in review meetings

Planning and Cost Engineer at Al Hamra Kuwait Co. W.L.L
  • Kuwait
  • March 2012 to February 2014

Project 1 : GAK Hawk Base Design-Build Project, Iraq Project value : 14 million USD Design and renovate a commercial power distribution system, water distribution system, renovation of buildings for Iraq Air Force in Hawk base. Utilities improvement in new Muthana Air Base. Client : US Army Corps of Engineers
•Prepare Baseline schedule as per "Network Analysis Schedule" requirements by US Army Corps of Engineers (USACE)
•Time Impact analysis for changes in contract, variance request, and claim
•Cost & resource loading
•Monthly Network Analysis updates with reports
•Tracking progress and 3-week lookahead schedule
•Earned value reports.
•Proposals for contract modifications - Fragnet & Cost proposal.

Planning Engineer at Galfar Engineering & Contracting SAOG
  • United Arab Emirates
  • July 2008 to March 2010

Education

Bachelor's degree, Civil Engineering
  • at Bangalore University
  • December 2000

Specialties & Skills

Value Engineering
Construction
Primavera
Network Analysis
BRIDGES
CONSTRUCTION DESIGN AND MANAGEMENT (CDM) REGULATIONS
POWER DISTRIBUTION
PRIMAVERA (SOFTWARE)
RENOVATION
MANAGEMENT
CONSTRUCTION
LOOKAHEAD
RESOURCE LOADING
NETWORK ANALYSIS