Work Experience

Total years of experience :13 years, 0 Months

Lead Planning Engineer at Saiif Bin Darwish
  • United Arab Emirates - Abu Dhabi
  • My current job since March 2016

Developing Baseline program with detailed Work Breakdown Structure (WBS), Network diagram, Critical path, milestones & project deliverables by effectively communicating with all stakeholders involved and ensuring consistency with contract
documents (Conditions of Contract, Specifications, Bill of Quantities, Drawings and Method Statement).
Reprogramming the tender activities on the basis of actual project requirement and developing baseline schedule with all manpower, material & equipment resources and cost loading the program in Primavera P6.
Preparing Recovery program and Three Week Look Ahead programs as per construction requirement for effective project administration.
Tracking the baseline by ensuring that the project schedule is being updated on periodical basis and supporting project manager and site team to build the deliverables on time.
Monitoring the progress and analyzing project progress versus baseline program and identifying / forecasting delays to mitigate risks to take preventive action.
Reporting KPI’s (Key Performance Indicators) comprising Engineering deliverables like Design status, shop drawing performance, procurement performance and publishing Project Dashboard.
Measuring the outturn efficiency of each team and alerting the construction manager if any substandard output for a particular period found which has the time and cost implications on project.
Coordinating with design consultant Bilfinger Tebodin to get the concept design, preliminary design and detailed design approved by Etihad Rail (Etihad Rail is one of the Stakeholder in this Project).
Attending progress meetings with client and making presentation about the project progress in areas like Engineering Submittals, Approvals, Material, Shop drawings, method statements and NOC. Attending Review meetings with client & consultant to discuss project issues, performance, requirement and technical & commercial aspects of project delivery.
Assisting project manager in drafting correspondence letters and replying client emails.

Planning Engineer at Samsung Engineering
  • Saudi Arabia - Yanbu
  • May 2014 to February 2016

1. Developing detailed Work Breakdown Structure (WBS), Network diagram, Critical path, milestones & project deliverables by effectively communicating with all stakeholders involved and ensuring consistency with contract documents (Conditions of Contract, Specifications, Bill of Quantities, Drawings and Method Statement).
2. Reprogramming the tender activities on the basis of actual project requirement and formulating baseline schedule with all manpower, material & equipment resources and cost loading the program in Primavera P6.
3. Preparing Target construction Program (TCP), Micro programs, Mini schedules and look-ahead programs as per construction requirement for effective project administration.
4. Tracking the baseline by ensuring that the project schedule is being updated on periodical basis and supporting project manager and site team to build the deliverables on time.
5. Monitoring the progress and analyzing project progress versus baseline program and identifying / forecasting delays to mitigate risks to take preventive action.
6. Performing Critical Path Methodology (CPM) and following-up with Project and Construction Managers and advising them regarding the activity falling on critical path and its effect on other activities in schedule if delayed.
7. Analyzing overall project performance using Earned Value Management (EVM) and Key Performance Indexes (KPI’s) by investigating the schedule and advising the team on cost variance (CV) and schedule variance (SV) and preparing forecasts resulting from significant deviations from scheduled baselines and identifying shortcomings.
8. Liaising with Project Manager and making recovery plans, monitoring implementation and ensuring the project completion within the specified duration and supporting the project Manager's decision-making process providing all information necessary for a rapid identification of unfavorable trend or potential problem in time in order to start immediate corrective actions.
9. Coordinating with Procurement engineer to update the procurement schedule & material delivery status.
10. Preparing monthly cash flow statements and making Cash 'S' curve chart, histograms and Gantt charts.
11. Attending review meetings with client and consultant to discuss project site issues, program thresholds, risks, variations, escalation etc.
12. Preparing as built schedule and closure reports for each structure.

Planning & Cost Engineer at GP Zachariades Engineering & Construction
  • Bahrain - Manama
  • May 2011 to April 2014

1. Preparing daily progress report (DPR), monthly progress report (MPR), project performance report (cash in & cash out statement) & management information system (MIS) Reports.
2. Planning day, week and month wise program and incorporating with resource schedule including manpower, materials required, area of formwork required, Plant & equipment required to complete the activity.
3. Developing Target Construction Program through logical sequence of activities as per client’s delivery requirement.
4. Planning of all construction activities involved in work package & tracking the same on daily basis with actuals.
5. Preparing balance program and resource requirement to complete the project.
6. Monitoring site work progress with respect to the baseline schedule.
7. Preparing & monitoring procurement schedule for procuring materials and delivery.
8. Liaising with various departments and doing follow-up with Procurement department for material, drawing team for shop drawing.
9. Developing Look-ahead programs for three weeks and three months
10. Liaising with technical team to support project requirements at all stages.
11. Tracking the Project status by updating the baseline schedule with actual dates of the activities.
12. Maintaining healthy relationship with Clients, Subcontractors and team members.
13. Effective communication with the team to close any technical issue arising and taking immediate action on client’s requirements and priority.
14. Coordinating with document controller and documenting all correspondences (to and from) with respect to project planning.
15. Assisting commercial team in project closeout for Final valuation by preparing re-measurement takeoff, bar bending schedule, submitting checklists & pour-cards, as built survey records, as built schedule records, guaranty certificates etc.
16. Preparing Cost report on weekly basis and generating consolidated report for monthly reconciliation.
17. Preparing Sub contractor reconciliation report by comparing the paid quantity (amount) to subcontractor versus claimed quantity (amount) from client.
18. Preparing Material reconciliation report by comparing the theoretical consumption of material against a BOQ (Bill of quantity) item versus actual consumption of material.

Education

Bachelor's degree, BE Civil Engineering
  • at JJ College of Engineering & Technology
  • April 2007

AWARDS: FIRST Prize in 'Technical Quiz' in National level Symposium HONORS: Semi Finalist In State Level Athletics Meet in 110m Hurdles PROJECTS/THESIS/SEMINARS: • Design of Multipurpose Indoor Sports Stadium using “REVIT” Architecture. • National level Technical seminar on “EQ Resistant Structures”

Specialties & Skills

Primavera P6
Refinery
Oil and Gas
Sewage Treatment Plant
Refinery
Project Scheduling Monitoring & Control
Primavera P6
MS Project
MS Office
Thermal Power Plant
Earned Value Management
Risk Analysis & Risk Management
Delay claims & Time Impact Analysis
Critical Path Method and Precedence Network Analysis
Performance Report,Progress Report,Day wise Program,Cash Flow Statement, S curve
Asta Power Project
Measurement claims, EOT claims, Pricing, Procurement schedule
Measurement takeoff, Material takeoff, Cost Analysis, Resource Estimation
Water Treatment Plant
Planning

Languages

English
Expert

Memberships

ICAN Association
  • Member
  • September 2008
Project Management Institute
  • Project Management Professional
  • May 2014

Training and Certifications

Project Management Professional (Certificate)
Date Attended:
May 2014

Hobbies

  • Athletics
    CHAMPIONSHIP in Zone, 200m FIRST in zone, Long Jump FIRST in zone, 110m Hurdles SECOND in zone, Triple jump THIRD in zone,
  • Volleyball
    Runnerup in Zone
  • Chess
    District FIRST. State level participation. 10th rank in Open chess tournament