Site Manager
TRACTEBEL Engineering pvt ltd
Total years of experience :18 years, 5 Months
of 100MW(AC) Solar PV Plant
of 24MW(AC) Solar PV Plant
of 341(NET) MW CCPP
of 344(NET) MW CCPP
Done Assignment in (Summit Meghnaghat Power Company Limited (337 MW/ 305 MW (Net) Dual fuel combined cycle power plant, Loc: Dhaka, Bangladesh) (
Site supervision of 4*350 MW TPP
Site supervision of 2*60 MW TPP
Site supervision of LV Substation
Automatic voltage regulator
Unitrol - China
Employment Record:
Organisation
Year (From - To)
Key responsibilities
Generator circuit breaker
ABB - China
•Project Management, Engineering Coordination, Quality Assurance and Project execution of ground based solar projects upto 130MW (DC)/100MW (AC).
Countries of work experience
India
Passport No.
P7050450
ACME-Gurgoan
Doing Assignment in 130MW (DC)/100MW (AC) Solar PV Project as
Done Assignment in 30MW(AC) Solar PV Project as
Done Assignment in Suprasana Solar energy Pvt Limited 24MW (AC) Solar PV Project as
Workedas owner’s engineer in 4*350 MW GMR kamalanga thermal power plant in Dhenkanal, Orissa, India.
Done site supervision of BTG area (Generator(350MW), AVR, IPBD(20kV), SPBD(6.6v), NSPBD(430v), GCB, generator transformer (420MVA), Unit auxiliary transformer’s (upto 33MVA), Unit and common switchgear panel’s (6.6kV), cable laying and cable tray works).
Done site supervision of 400kV switchyard and inspected erection and testing reports of switchyard equipments (isolator, CT, CVT, CB..etc., ) and done scheme checking of switchyard (one and half breaker scheme).Done field quality inspections of equipment (electrical and mechanical).
Prepared FQP (field quality plan) documents related to electrical equipment of plant (BTG & BOP).
Done field quality inspection as per the quality plan and issued the NCR (non conformance report) related issues of electrical to EPC contractor.
Done MOM with contractor and
Worked in 2*60 MW IPP Orissa, india
for construction of 33/11kV substation in Bhadrachalem, Andhra Pradesh
Supervising the activities of erection of CT, CVT, CB, Isolator, T/F, BUS and electrical Panel in site.
Done site testing of electrical equipments as per the standard’s.
Preparation of daily progress report.
Co-ordination with team members.
Daily updating the manpower report at site.
Done MOM with client regarding site construction.
(
(