Recent Major Projects:
Ras Tanura Integrated Project (RTIP), Jubail Industrial City, KSA.
Saudi Aramco, one of the leading energy suppliers to the world, and The Dow Chemical Company, a leading science and technology company of the world, have formed a joint venture, Sadara Chemical Company (Sadara), which will construct, own and operate a world-scale integrated chemicals complex in Jubail Industrial City II, in the Eastern Province of the Kingdom of Saudi Arabia.
Once completed, the Sadara complex will be one of the world’s largest integrated petrochemical facilities and largest ever built in a single phase. Sadara and the adjoining PlasChem Park will establish a world-scale manufacturing footprint that delivers a full range of value-added, performance products destined for the emerging markets of Asia Pacific, the Middle East, Eastern Europe and Africa.
Client : Saudi Aramco & The Dow Chemical Company (Sadara)
Consultant : Japan Gas Company (JGC Corp.)
Software used : PRIMAVERA Project Planner (P6.0, R8.2)
RESPONSIBILITIES:
Preparing the construction schedule in Primavera P6 and also preparation of other planning documents like Progress “S” Curve, Earn Value Curve, Man power Histogram etc.
Understanding project work scope, needs and deliverables, contract milestones, Estimating budget quantities, costs, durations and resources
Preparation of Base line Project Schedule and Budget Loading.
Preparation of overall construction program, monitoring project progress against planned schedules, analysis in the change of contract scope / delay, if any, etc.
Preparation of monthly progress reports, look-ahead programs, bar charts, S-curve, floating enquiries etc.
Preparing Cost curve based on Cash flow.
Preparing Contract Performance Chart of the project.
Cost loading and Resource assignment on monthly basis.
Allocation of Man power for getting optimal result.
Managed design of EBS and OBS for P6.
Designing of WBS and assigning of activity codes for activities.
Managing migration from P3 to P6(Primavera Project Enterprise)
Well versed with Threshold and Issue Analysis in P6.
Knowledge of Risk Analysis.
Capable of Top down Estimation.
Preparation of daily and weekly status reports.
Preparing Monthly Progress reports of various subsystems for submission.
Doing Causal Analysis for bottleneck elimination.
Preparation of Change Control Report using Primavera Claim Digger.
Preparation of various types of MIS reports for Top Management.