Expansion of an existing 5* Hotel, Project Budget: 3.000.000 €
Duties:
Totally involved in the procurement procedure of the project ( construction costs, rides costs, utilities costs etc.)
Initial design and conception of the project
Supervision of a complete construction of a large scale Water Park,
Supervising and coordinating construction team,
Keeping daily records,
Controlling daily progress of the construction and solving various problems that appeared during the construction.
Production of measurements tables and cost tables for final payments.
Setting out of buildings and structures,
Comply with H&S regulations,
Design and checking all final construction drawings and details,
Representing the company in meetings with client and architects. .
Choosing sub-contractors,
Pre-construction production of time schedule
• Developing a cost-effective plan and schedule for completion of projects following a logical pattern for utilization of resources.
• Selecting and coordinating work of subcontractors working on various phases of the project.
• Overseeing performance of all trade contractors and reviewing architectural and engineering drawings to make sure that all specifications and regulations are being followed.
• Responsible for proper administration of construction contracts and for obtaining all necessary permits and licenses.
• Supervising assistants, reviewing their reports, checking on any reported difficulties, and correcting any safety violations or other reported deficiencies.
• Tracking and controlling construction schedules and associated costs to achieve completion of project within time and monies allocated.
• Reporting to owners and architects about progress and any necessary modifications of plans.
• Completion and final handover of project.
Renovation of a 4* Hotel, Project Budget: 2.000.000 €
Duties:
Totally involved in the procurement procedure of the project ( construction costs, rides costs, utilities costs etc.)
Initial design and conception of the project
Supervision of a complete construction of a large scale Water Park,
Supervising and coordinating construction team,
Keeping daily records,
Controlling daily progress of the construction and solving various problems that appeared during the construction.
Production of measurements tables and cost tables for final payments.
Setting out of buildings and structures,
Comply with H&S regulations,
Design and checking all final construction drawings and details,
Representing the company in meetings with client and architects. .
Choosing sub-contractors,
Pre-construction production of time schedule
• Developing a cost-effective plan and schedule for completion of projects following a logical pattern for utilization of resources.
• Selecting and coordinating work of subcontractors working on various phases of the project.
• Overseeing performance of all trade contractors and reviewing architectural and engineering drawings to make sure that all specifications and regulations are being followed.
• Responsible for proper administration of construction contracts and for obtaining all necessary permits and licenses.
• Supervising assistants, reviewing their reports, checking on any reported difficulties, and correcting any safety violations or other reported deficiencies.
• Tracking and controlling construction schedules and associated costs to achieve completion of project within time and monies allocated.
• Reporting to owners and architects about progress and any necessary modifications of plans.
• Completion and final handover of project.
New-Built Junction inside an existing 4* hotel, Project Budget: 780.000 €
Duties:
Totally involved in the procurement procedure of the project ( construction costs, rides costs, utilities costs etc.)
Initial design and conception of the project
Supervision of a complete construction of a large scale Water Park,
Supervising and coordinating construction team,
Keeping daily records,
Controlling daily progress of the construction and solving various problems that appeared during the construction.
Production of measurements tables and cost tables for final payments.
Setting out of buildings and structures,
Comply with H&S regulations,
Design and checking all final construction drawings and details,
Representing the company in meetings with client and architects. .
Choosing sub-contractors,
Pre-construction production of time schedule
• Developing a cost-effective plan and schedule for completion of projects following a logical pattern for utilization of resources.
• Selecting and coordinating work of subcontractors working on various phases of the project.
• Overseeing performance of all trade contractors and reviewing architectural and engineering drawings to make sure that all specifications and regulations are being followed.
• Responsible for proper administration of construction contracts and for obtaining all necessary permits and licenses.
• Supervising assistants, reviewing their reports, checking on any reported difficulties, and correcting any safety violations or other reported deficiencies.
• Tracking and controlling construction schedules and associated costs to achieve completion of project within time and monies allocated.
• Reporting to owners and architects about progress and any necessary modifications of plans.
• Completion and final handover of project.
Construction of a very large Water Park inside an existing luxury resort.
Construction of a 4.000.000 euros new built water park.
Renovation of an existing 4 star luxury hotel complex.
01/05/2012-30/10/2012: Position: Engineering Manager
Company: DSK Dimitris Sifonios technical office, Kos Island
Project: Several structural designs
10/01/2012-30/04/2012: Position: Construction Manager
Company: DSK Dimitris Sifonios technical office, Kos Island
Project: Water Park, Kipriotis Village (5 stars hotel), Project Budget: 5.000.000 €
Location: Kos Island, Greece
Duties: * Supervision of a large water park of an existing hotel,
* Supervising and coordinating construction team,
* Keeping daily records,
* Controlling daily progress of the construction and solving various problems that appeared during the construction.
* Production of measurements tables and cost tables for final payments.
* Setting out of buildings,
* Comply with H&S regulations,
* Design and checking all final construction drawings and details,
* Representing the company in meetings with client and architects.
* Choosing sub-contractors,
* Pre-construction production of time schedule
• Developing a cost-effective plan and schedule for completion of projects following a logical pattern for utilization of resources.
• Selecting and coordinating work of subcontractors working on various phases of the project.
• Overseeing performance of all trade contractors and reviewing architectural and engineering drawings to make sure that all specifications and regulations are being followed.
• Responsible for proper administration of construction contracts and for obtaining all necessary permits and licenses.
• Supervising assistants, reviewing their reports, checking on any reported difficulties, and correcting any safety violations or other reported deficiencies.
• Tracking and controlling construction schedules and associated costs to achieve completion of project within time and monies allocated.
• Reporting to owners and architects about progress and any necessary modifications of plans.
15/09/2011-17/12/2011: Position: Construction Manager
Company: DSK Dimitris Sifonios technical office, Kos Island
Project: Construction of two large commercial warehouses, Budget: 1.000.000 €
Location: Kos Island, Greece
Duties: * Design and supervision of two large steel commercial ware houses
* Supervising and coordinating construction team,
* Keeping daily records,
* Controlling daily progress of the construction and solving various problems that appeared during the construction.
* Production of measurements tables and cost tables for final payments.
* Setting out of buildings,
* Comply with H&S regulations,
* Design and checking all final construction drawings and details,
* Representing the company in meetings with client and architects.
* Choosing sub-contractors,
* Pre-construction production of time schedule
• Developing a cost-effective plan and schedule for completion of projects following a logical pattern for utilization of resources.
• Selecting and coordinating work of subcontractors working on various phases of the project.
• Overseeing performance of all trade contractors and reviewing architectural and engineering drawings to make sure that all specifications and regulations are being followed.
• Responsible for proper administration of construction contracts and for obtaining all necessary permits and licenses.
• Supervising assistants, reviewing their reports, checking on any reported difficulties, and correcting any safety violations or other reported deficiencies.
• Tracking and controlling construction schedules and associated costs to achieve completion of project within time and monies allocated.
• Reporting to owners and architects about progress and any necessary modifications of plans.
10/01/2011-12/05/2011: Position: Construction Manager
Company: DSK Dimitris Sifonios technical office, Kos Island
Project: Porto Bello Hotel (4 stars hotel), Project Budget: 2.000.000 €
Location: Kos Island, Greece
Duties: * Design and supervision of a medium expansion of an existing hotel
* Supervising and coordinating construction team,
* Keeping daily records,
* Controlling daily progress of the construction and solving various problems that appeared during the construction.
* Production of measurements tables and cost tables for final payments.
* Setting out of buildings,
* Comply with H&S regulations,
* Design and checking all final construction drawings and details,
* Representing the company in meetings with client and architects.
* Choosing sub-contractors,
* Pre-construction production of time schedule
• Developing a cost-effective plan and schedule for completion of projects following a logical pattern for utilization of resources.
• Selecting and coordinating work of subcontractors working on various phases of the project.
• Overseeing performance of all trade contractors and reviewing architectural and engineering drawings to make sure that all specifications and regulations are being followed.
• Responsible for proper administration of construction contracts and for obtaining all necessary permits and licenses.
• Supervising assistants, reviewing their reports, checking on any reported difficulties, and correcting any safety violations or other reported deficiencies.
• Tracking and controlling construction schedules and associated costs to achieve completion of project within time and monies allocated.
• Reporting to owners and architects about progress and any necessary modifications of plans.
16/10/2010-18/05/11: Position: Construction Manager
Company: DSK Dimitris Sifonios technical office, Kos Island
Project: Oceanis Resort and Spa (4 stars hotel), Project Budget: 25.000.000 €
Location: Kos Island, Greece
Duties: * Design and supervision of renovation of an existing hotel
* Supervising and coordinating construction team,
* Keeping daily records,
* Controlling daily progress of the construction and solving various problems that appeared during the construction.
* Production of measurements tables and cost tables for final payments.
* Setting out of buildings,
* Comply with H&S regulations,
* Design and checking all final construction drawings and details,
* Representing the company in meetings with client and architects.
* Choosing sub-contractors,
* Pre-construction production of time schedule
• Developing a cost-effective plan and schedule for completion of projects following a logical pattern for utilization of resources.
• Selecting and coordinating work of subcontractors working on various phases of the project.
• Overseeing performance of all trade contractors and reviewing architectural and engineering drawings to make sure that all specifications and regulations are being followed.
• Responsible for proper administration of construction contracts and for obtaining all necessary permits and licenses.
• Supervising assistants, reviewing their reports, checking on any reported difficulties, and correcting any safety violations or other reported deficiencies.
• Tracking and controlling construction schedules and associated costs to achieve completion of project within time and monies allocated.
• Reporting to owners and architects about progress and any necessary modifications of plans.
• Blue Lagoon Village, 5 stars (2010-2011) (Kos-Greece)
01/06/2010-15/10/2010: Position: Structural Manager
Company: DSK Dimitris Sifonios technical office, Kos Island
Duties: supervision of three design engineers for the design of detail structural and architectural drawings for multistory R/C buildings (commercial, residential, offices, hotels), Planning of the construction of various new projects. Value engineering,
30/09/2009-30/05/2010: Position: Construction Manager
Company: DSK Dimitris Sifonios technical office, Kos Island
Project: Blue Lagoon Resort (5 stars hotel), Project Budget: 11.790.000 €
Location: Kos Island, Greece
Duties: * Design and supervision of construction of expansion of an existing hotel
* Supervising and coordinating construction team,
* Keeping daily records,
* Controlling daily progress of the construction and solving various problems that appeared during the construction.
* Production of measurements tables and cost tables for final payments.
* Setting out of buildings,
* Comply with H&S regulations,
* Design and checking all final construction drawings and details,
* Representing the company in meetings with client and architects.
* Choosing sub-contractors,
* Pre-construction production of time schedule
• Developing a cost-effective plan and schedule for completion of projects following a logical pattern for utilization of resources.
• Selecting and coordinating work of subcontractors working on various phases of the project.
• Overseeing performance of all trade contractors and reviewing architectural and engineering drawings to make sure that all specifications and regulations are being followed.
• Responsible for proper administration of construction contracts and for obtaining all necessary permits and licenses.
• Supervising assistants, reviewing their reports, checking on any reported difficulties, and correcting any safety violations or other reported deficiencies.
• Tracking and controlling construction schedules and associated costs to achieve completion of project within time and monies allocated.
• Reporting to owners and architects about progress and any necessary modifications of plans
04/06/2008-15/07/2009: Position: Construction Manager
Company: DSK Dimitris Sifonios technical office, Kos Island
Project: Diamond Deluxe Hotel and Spa (5 stars hotel), Project Budget: 22.000.000 €
Location: Kos Island, Greece
Duties: * Design and supervision of construction of a new built hotel
* Supervising and coordinating construction team,
* Keeping daily records,
* Controlling daily progress of the construction and solving various problems that appeared during the construction.
* Production of measurements tables and cost tables for final payments.
* Setting out of buildings,
* Comply with H&S regulations,
* Design and checking all final construction drawings and details,
* Representing the company in meetings with client and architects.
* Choosing sub-contractors,
* Pre-construction production of time schedule
• Developing a cost-effective plan and schedule for completion of projects following a logical pattern for utilization of resources.
• Selecting and coordinating work of subcontractors working on various phases of the project.
• Overseeing performance of all trade contractors and reviewing architectural and engineering drawings to make sure that all specifications and regulations are being followed.
• Responsible for proper administration of construction contracts and for obtaining all necessary permits and licenses.
• Supervising assistants, reviewing their reports, checking on any reported difficulties, and correcting any safety violations or other reported deficiencies.
• Tracking and controlling construction schedules and associated costs to achieve completion of project within time and monies allocated.
• Reporting to owners and architects about progress and any necessary modifications of plans.
16/07/2007-03/06/2008: Position: Construction Manager
Company: DSK Dimitris Sifonios technical office, Kos Island
Project: Palazzo del Mare Hotel (5 stars Hotel), Project Budget: 16.920.000 €
Location: Kos Island, Greece
Duties: * Design and supervision of construction of a new built luxury hotel
* Supervising and coordinating construction team,
* Keeping daily records,
* Controlling daily progress of the construction and solving various problems that appeared during the construction.
* Production of measurements tables and cost tables for final payments.
* Setting out of buildings,
* Comply with H&S regulations,
* Design and checking all final construction drawings and details,
* Representing the company in meetings with client and architects.
* Choosing sub-contractors,
* Pre-construction production of time schedule
• Developing a cost-effective plan and schedule for completion of projects following a logical pattern for utilization of resources.
• Selecting and coordinating work of subcontractors working on various phases of the project.
• Overseeing performance of all trade contractors and reviewing architectural and engineering drawings to make sure that all specifications and regulations are being followed.
• Responsible for proper administration of construction contracts and for obtaining all necessary permits and licenses.
• Supervising assistants, reviewing their reports, checking on any reported difficulties, and correcting any safety violations or other reported deficiencies.
• Tracking and controlling construction schedules and associated costs to achieve completion of project within time and monies allocated.
• Reporting to owners and architects about progress and any necessary modifications of plans.
21/06/2007-15/07/2007: Position: Structural Engineer
Company: DSK Dimitris Sifonios technical office, Kos Island
Duties: Design of detail structural and architectural drawings for multistory R/C buildings (commercial, residential, offices, hotels)
11/04/2005-20/06/2007: Position: Construction Engineer-Site manager
Company: DSK Dimitris Sifonios technical office, Kos Island
Project: Renovation of Caravia Beach Hotel (4 star Hotel), Project Budget: 24.460.000 €
Location: Kos island, Greece
Duties: * Design and supervision of the renovation
* Supervising and coordinating construction team
* Keeping daily records
* Checking daily progress of the construction work and solving various problems that appeared during the construction
* Production of measurement tables and cost tables for final payments
* Setting out of buildings
* Comply with H&S regulations
* Design and checking all final construction drawings and details.
14/02/2005-10/04/2005: Position: Civil Engineer
Company: DSK Dimitris Sifonios technical office, Kos Island
Duties: Design of detail structural and architectural drawings for multistory R/C buildings (commercial, residential, offices, hotels)
20/04/2004-20/01/2005: Position: Civil Engineer
Company: Kostas Dimitris, Athens
Duties: Supervision of retrofit and maintenance works in various commercial and army buildings in Athens district
15/06/2003- 30/08/2003: Position: Trainee Civil Engineer
Company: MSc Komiotis George, Zakynthos
Duties: Design of detail structural and architectural drawings for R/C residential buildings, on site visits for QA/QC issues
15/06/2002- 30/08/2002: Position: Trainee Civil Engineer
Company: MSc Komiotis George, Zakynthos
Duties: Design of detail structural and architectural drawings for R/C residential buildings, on site visits for QA/QC issues
15/06/2000 - 30/08/2000: Position: Trainee Civil Engineer
Company: Dr. Liveris Stamatis, Zakynthos
Duties: Design of detail structural and architectural drawings for R/C residential buildings
During my time at DSK company I was also involved in the structural design and analysis, value engineering, pre-construction time scheduling, procurent engineering and dealing with subcontractors, of the following projects: • Michelangelo Hotel, 5 stars (2009) (Kos-Greece)
• Xenia Village, 5 stars (2010) (Patmos-Greece)
2003 - 2004 MSc in Civil and Earthquake Engineering - University of Liverpool UK
1999 - 2003 BHons in Civil Engineering- University of Liverpool UK