Review the Contactor’s submitted detailed Baseline Construction Schedule to ensure that all aspects of works from Engineering, Procurement, Mobilization, Construction, Fabrication, Installation and Turn-over are incorporated and align with the Bill of quantities and contract.
Review the contractor’s submitted Histograms, S‐Curves, Cost/ Resource Loading and Look‐ahead Schedules to ensure that the design and forecasting of accomplishment to meet the target milestone are included.
Review & analyzing the critical path of the project and identify if there are probable occurring risk to prevent any possible delay.
Review and track the contractor’s progress update using Value of Work done ( Earned Value Management analysis)
Close tracking of the procurement and delivery schedule specially the long lead items to ensure that it is planned and in accordance with the construction sequence.
Review and recommend to the client for final approval of the contractor’s justification on the claim for extension of time (EOT)
Assisting the client’s intension for fine tuning of Project Management Information Systems.
Conducting ocular site inspection to ensure that the flow of work is in accordance with the project methodology and priorities according to work sequence
Prepare Tender Preliminary schedule including Project Codes, Activity Codes and WBS Codes
Prepare Histograms, S‐Curves, Resource Loading and Look‐ahead Schedules which include the design and forecasting of accomplishment to meet the target milestone.
Reviewing & Analyzing the critical path of the assigned project then recommend solution to avoid delay
Prepare progress update using Earned Value Management
Ensure that the procurement and delivery schedule are well planned and in accordance with the construction sequence.
Conducting ocular site inspection to ensure that the flow of work is in accordance with the project methodology and priorities according to work sequence
Prepare Baseline for Preliminary and Detailed schedule including Project Codes, Activity Codes and WBS Codes
Continuously monitor and update the current work progress
Prepare Histograms, S‐Curves, Resource Loading and Look‐ahead Schedules which include the design and forecasting of accomplishment to meet the target milestone.
Reviewing & Analyzing the critical path of the assigned project then recommend solution to avoid delay
Conducting Delay/Time Impact Analysis as per change order
Prepare progress update using Earned Value Management
Ensure that the procurement and delivery schedule are well planned and in accordance with the construction sequence.
Conducting ocular site inspection to ensure that the flow of work is in accordance with the project methodology and priorities according to work sequence
Prepare Master schedule using P6 software
Prepare daily accomplishment report
Responsible for Building Superstructures including structural design, earthworks, controls & verticality of steel columns, alignment of beams & girders
Responsible for Architectural Finishes
Prepare and Implement the project schedules and methodology
Prepare the required project resources
Review drawings, specifications and commitment dates during tendering stage
Prepare scope of work.
Prepare a level 1 plan and regular updates.
Prepare Baseline schedule of assigned area of responsibility and continuously monitor the current work progress
Reviewing & Analyzing the critical path of the project
Analyze the project status and reports conclusion to the Project Manager
Provide planning reports and narratives in accordance with the Planning scope of work
Responsible for obtaining the information that is needed to make and maintain the project plan
Prepare Project Codes, Activity Codes and WBS Codes
Prepare Histograms, S‐Curves, Resource Loading and Look‐ahead Schedules which include the design and forecasting of accomplishment to meet the target milestone.
Prepare progress update using Earned Value Management
Conducting subjective monitoring to ensure the actual progress
Prepare Baseline schedule of assigned area of responsibility and continuously monitor the current work progress
Prepare Stand-Alone schedule for “Shutdown” works
Reviewing & Analyzing the critical path of the project
Analyze the project status and reports conclusion to the Project Manager
Maintains project schedule by monitoring project progress, coordinating activities and resolving problems.
Responsible in Road construction (concrete, asphalt).
Responsible in Drainage system construction
Responsible in shutdown activities of assigned area in relation to Oil tank & vessel cleaning, replacement of pipelines and provision of bypass pipelines.
Responsible in construction of pipe slippers, pipe rack for 12” FRP Fresh water lines and 8” cast iron industrial waste line system.
Responsible in Civil works activity for erection of 2.5MGD fresh water tanks.
Responsible in construction of sub-station, control building, cable trenches, duct bunks and direct buried PVC pipes.